INSP-Final Inspection | 11/21/2013 | 11/21/2013 | 11/21/2013 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit work completed and passed final walkthrough.
|
INSP-Sprinkler Rough-in | 11/18/2013 | 11/18/2013 | 11/18/2013 | P | PART |
Forrest France
|
|
|
Overhead work passed rough-in
|
INSP-Sprinkler Rough-in | 9/11/2013 | 9/12/2013 | 9/12/2013 | A | PART |
Forrest France
|
|
|
Inspection for hanger attatchments above the sheetrock lid in the three new rooms at the production area okayed for cover. Also completed rough-in for the new and relocated uprights due to wall construction.
|
Permit Ready to Issue | | | 8/29/2013 | | |
|
|
|
|
Inspection Record Card- Fire | 8/29/2013 | | 8/29/2013 | | DONE |
Darla L Downs
|
|
|
|
Issue and Print Permit | | | 8/29/2013 | | DONE |
|
|
|
|
Sprinkler Plan Check | 8/28/2013 | | 8/28/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/28/2013 | | DONE |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 8/27/2013 | | 8/27/2013 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 8/27/2013 | | 8/27/2013 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 8/27/2013 | | FAIL |
|
|
|
|
Miscellaneous action | | | 8/27/2013 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 8/26/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 26 2013 2:43PM
|