INSP-Final Inspection | 10/31/2013 | 11/1/2013 | 11/1/2013 | A | PASS |
Forrest France
|
|
|
Scope of work completed. Final walkthrough passed. Flow switch at the existing riser to be repaired prior to project related building permit final.
|
INSP-Sprinkler Rough-in | 10/9/2013 | 10/9/2013 | 10/9/2013 | P | PART |
Forrest France
|
|
|
Remainder of the overhead work at the pharmacy and west lower ceiling retail areas passed rough-in and are approved for cover. Verified balance of branchline restraints are installed in the high bays, drops at cloud ceilings okayed. Need to provide coverage at the SW exit vestibule, remove travel caps at drops, install escutcheons and field ceiling tile prior to permit final.
|
INSP-Sprinkler Rough-in/Hydro | 9/24/2013 | 9/30/2013 | 9/30/2013 | A | PART |
Forrest France
|
|
|
Overhead hydrostatic test completed satisfactory. Also finished rough-in at the high bay sales floor area only- EQ bracing and seismic branchline restraints are not yet finished.
|
Permit Ready to Issue | | | 9/12/2013 | | |
|
|
|
|
Inspection Record Card- Fire | 9/12/2013 | | 9/12/2013 | | DONE |
Darla L Downs
|
|
|
|
Issue and Print Permit | | | 9/12/2013 | | DONE |
|
|
|
|
Sprinkler Plan Check | 9/6/2013 | | 9/6/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/6/2013 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 8/28/2013 | | 8/28/2013 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 8/28/2013 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 8/28/2013 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Plan assigned to (Tim) | 8/27/2013 | | 8/27/2013 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 8/26/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 26 2013 3:12PM
|