INSP-Final Inspection | 11/15/2013 | 11/15/2013 | 11/15/2013 | P | PASS |
Forrest France
|
|
|
Scope of work completed. Fire sprinkler permit okayed for final.
|
INSP-Sprinkler Rough-in | 10/22/2013 | 10/23/2013 | 10/23/2013 | A | PART |
Forrest France
|
|
|
Remainder of overhead work per the permit scope passed rough-in inspection. Previous adjustments and correction items also completed.
|
INSP-Sprinkler Rough-in | 9/19/2013 | 9/20/2013 | 9/20/2013 | P | PART |
Forrest France
|
|
|
Okay to cover fire sprinkler work above the sheetrock lids as marked on approved plans. Need to revise coverage at the office, provide intermediate temp heads within the fireplace zone of influence, coolers/DP are not yet installed.
|
Plan assigned to (Tim) | 9/17/2013 | | 9/17/2013 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 9/17/2013 | | 9/17/2013 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 9/17/2013 | | FAIL |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 9/17/2013 | | 9/17/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/17/2013 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 9/17/2013 | | DONE |
Christina Prado
|
|
|
|
Issue and Print Permit | | | 9/17/2013 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 9/17/2013 | | 9/17/2013 | | DONE |
Christina Prado
|
|
|
|
Application received | | | 9/16/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 16 2013 3:22PM
|