INSP-Final Inspection | 8/27/2014 | 8/28/2014 | 8/28/2014 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
Miscellaneous action | | | 8/5/2014 | | DONE |
|
|
|
As Built drawings dataed 8-1-14 received and uploaded into projectdox.
|
INSP-Final Inspection | 7/31/2014 | 8/1/2014 | 8/1/2014 | P | FAIL |
Troy Cobbley
|
|
|
Owner wanted us to reschedule due to the crowds. I noted that 14 guage wire was installed not 12 guage as per the approved plans. Also the 75cd ceiling mounted horn/strobes need to have reduced spacing due to the height at which they have been installed. Also the 110cd ceiling moiunt strobe at teh very end of the tenant space is overspaced off of the wall in the picnic table area. And the NAC panel has been relocated to a different location in the building. No actual testing was performed.
|
Miscellaneous action | | | 7/14/2014 | | DONE |
|
|
|
I emailed Charlie Bayne to let him know this permt had exired without a final inspection. He responded to say that they will schedule the final for some time next week.
|
Case Summary | | | 9/25/2013 | | DONE |
|
|
|
|
1st review completed | | | 9/23/2013 | | PASS |
Lee G Meredith
|
|
|
|
Alarm Plan Check | 9/23/2013 | | 9/23/2013 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 9/23/2013 | | DONE |
Lee G Meredith
|
|
|
Plans approved. ProjectDox updated.
|
Permit Ready to Issue | | | 9/23/2013 | | DONE |
Christina Prado
|
|
|
|
Issue and Print Permit | | | 9/23/2013 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 9/23/2013 | | 9/23/2013 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (Lee) | 9/20/2013 | | 9/20/2013 | | DONE |
Lee G Meredith
|
|
|
|
Application received | | | 9/19/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 19 2013 3:31PM
|