Case Summary | | | 4/23/2014 | | |
|
|
|
|
Case Summary | | | 4/23/2014 | | |
|
|
|
|
INSP-Final Inspection | 4/8/2014 | 4/15/2014 | 4/15/2014 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 3/26/2014 | 3/27/2014 | 3/27/2014 | P | FAIL |
Troy Cobbley
|
|
|
Everything is complete except the unknown signals from zone one need addressed as per the fire dept.
|
INSP-Final Inspection | 2/25/2014 | 2/26/2014 | 2/26/2014 | A | FAIL |
Troy Cobbley
|
|
|
Provide weather proof cover for the annunciator, repair supervisory signal on zone 6 and provide updated map showing zone 1 as a spare and zone 10 being utilized.
|
INSP-Final Inspection | 12/16/2013 | 12/19/2013 | 12/19/2013 | A | CANC |
Troy Cobbley
|
|
|
Cancel per art Phone #: ###-####
|
INSP-Final Inspection | 12/16/2013 | 12/18/2013 | 12/18/2013 | A | FAIL |
Troy Cobbley
|
|
|
NAC circuit 1 has a "open" trouble, there is only one phone line, multiple strobes are overspaced, one strobe is blocked by movable partitions, I need verification that the strobes in the prep rooms are weatherproof and the remote annunciator (located outside) is weather proof, pull station in the crematorium is mounted too high. We did not set off the strobes to check sync. or test any devices since there was a trouble on the system and only one phone line.
|
INSP-Final Inspection | 11/22/2013 | 11/25/2013 | 11/25/2013 | A | FAIL |
Troy Cobbley
|
|
|
No inspection and testing form, no city approved plans or notes. Strobes would not function per Art. No testing performed.
|
Miscellaneous action | | | 9/30/2013 | | DONE |
Lee G Meredith
|
|
|
Received revised documentation. Smoke detectors will now also be replaced to meet UL compatability requirements that had previously been noted as an issue. Cross listing with the panel has been confirmed.
|
1st review completed | | | 9/30/2013 | | PASS |
Lee G Meredith
|
|
|
|
Alarm Plan Check | 9/30/2013 | | 9/30/2013 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 9/30/2013 | | DONE |
Lee G Meredith
|
|
|
Plans approved as noted. ProjectDox updated
|
Permit Ready to Issue | | | 9/30/2013 | | |
|
|
|
|
Inspection Record Card- Fire | 9/30/2013 | | 9/30/2013 | | DONE |
Darla L Downs
|
|
|
|
Issue and Print Permit | | | 9/30/2013 | | DONE |
|
|
|
|
Miscellaneous action | | | 9/26/2013 | | DONE |
|
|
|
Received proper submittal documents. In review, I noticed that the existing smoke detectors were not shown to be compatable with the new fire alarm panel that has been proposed. I emailed the applicant and requested documentation of cross listing.
|
Telephone call | | | 9/26/2013 | | DONE |
|
|
|
Phone call with troy Mansfield of Tyco. Discussed the requirement of cross listing of the existing detectors with the new, replacement panel. He informed me that he had been in touch with EST. They indicated that the detectors are listed with the panel and they will supply the document to him. When he receives it, they will update the case.
|
Miscellaneous action | | | 9/24/2013 | | DONE |
Lee G Meredith
|
|
|
Emailed applicant to inform them that a fire alarm panel replacement is not allowed to be performed with a quick permit application. They will need to resubmit with the appropriate application (form 601)
|
Application received | | | 9/23/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 23 2013 5:17PM
|