INSP-Final Inspection | 1/7/2014 | 1/10/2014 | 1/14/2014 | P | PASS |
Forrest France
|
|
|
Fire sprinkler walkthrough completed.
|
INSP-Final Inspection | 1/7/2014 | 1/8/2014 | 1/7/2014 | P | CANC |
Forrest France
|
|
|
Mike B is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Final Inspection | 12/9/2013 | 12/10/2013 | 12/11/2013 | P | PART |
Forrest France
|
|
|
Mike B is the contact. Phone #: ###-#### >> Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 10/17/2013 | 10/17/2013 | 10/18/2013 | P | PART |
Forrest France
|
|
|
Verified previous correction items are finished. Overhead fire sprinkler work okay to cover.
|
INSP-Sprinkler Rough-in | 10/16/2013 | 10/16/2013 | 10/16/2013 | P | PART |
Forrest France
|
|
|
Completed inspection for pendent heads at grid ceilings throughout the 7th floor. Need to install additional coverage at two storage rooms per the approved plan and hazard category, blocked coverage adjacent to the structural column in SW office #3. Remainder of work okayed for cover.
|
Plan assigned to (Tim) | 9/27/2013 | | 9/27/2013 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 9/27/2013 | | 9/27/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 9/27/2013 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/27/2013 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 9/27/2013 | | DONE |
|
|
|
|
Issue and Print Permit | | | 9/27/2013 | | |
|
|
|
|
Inspection Record Card- Fire | 9/27/2013 | | 9/27/2013 | | DONE |
Tisha Gallop
|
|
|
|
Application received | | | 9/25/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 25 2013 4:52PM
|