INSP-Final Inspection | 11/21/2013 | 11/22/2013 | 11/22/2013 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
CHANGE STATUS TO (ISS) | | | 10/29/2013 | | DONE |
Christina Prado
|
|
|
|
Alarm Plan Check | 10/28/2013 | | 10/28/2013 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 10/28/2013 | | DONE |
Lee G Meredith
|
|
|
Plan mod approved. ProjectDox updated.
|
Miscellaneous action | | | 10/24/2013 | | DONE |
|
|
|
Received an email from John Lopez informing me that the owner has decided to add visual notification to the balance of the floor. He wanted to know if this could be done under a plan modification or if it required a new permit submittal. I informed him that a plan modification would be better as it would allow the full floor upgrade to be contained in 1 drawing set and that product data resubmittal would be minimized. He informed me that he would provide a plan modificaiton.
|
Plan resubmittals received | | | 10/24/2013 | | DONE |
Lee G Meredith
|
|
|
Plan modification submitted to include full floor upgrade instead of just the Tax Commission portion of the floor.
|
Permit Ready to Issue | | | 10/4/2013 | | DONE |
Christina Prado
|
|
|
|
Issue and Print Permit | | | 10/4/2013 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 10/4/2013 | | 10/4/2013 | | DONE |
Christina Prado
|
|
|
|
1st review completed | | | 10/3/2013 | | PASS |
Lee G Meredith
|
|
|
|
Alarm Plan Check | 10/3/2013 | | 10/3/2013 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 10/3/2013 | | DONE |
Lee G Meredith
|
|
|
Plans approved as noted. ProjectDox updated.
|
Plan assigned to (Lee) | 10/2/2013 | | 10/2/2013 | | DONE |
Lee G Meredith
|
|
|
|
Application received | | | 9/27/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 27 2013 9:53AM
|