Miscellaneous action | | | 3/6/2014 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 10/16/2013 | 10/17/2013 | 10/17/2013 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit work passed final inspection.
|
INSP-Sprinkler Rough-in | 10/11/2013 | 10/14/2013 | 10/14/2013 | A | PART |
Forrest France
|
|
|
Okay to cover overhead fire sprinkler system modifications at the grid ceilings. Need to provide verification exisitng system is current with an annual inspection.
|
Plan assigned to (Tim) | 10/2/2013 | | 10/11/2013 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 10/11/2013 | | 10/11/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/11/2013 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 10/11/2013 | | 10/11/2013 | | DONE |
Darla L Downs
|
|
|
|
Permit Ready to Issue | | | 10/11/2013 | | |
|
|
|
|
Telephone call | | | 10/11/2013 | | |
|
|
|
10-11-13 called American Fire -permit ready and fee given ///dld
|
Issue and Print Permit | | | 10/11/2013 | | DONE |
|
|
|
|
Plan resubmittals received | | | 10/7/2013 | | |
|
|
|
10-7-13 received 3 sets of plans & 3 applications sent to Tim F.
|
Sprinkler Plan Check | 10/4/2013 | | 10/4/2013 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 10/4/2013 | | FAIL |
Tim Frost
|
|
|
|
Telephone call | | | 10/4/2013 | | DONE |
Christina Prado
|
|
|
Called office to advise resubs were needed for this project
|
Case Summary | | | 10/2/2013 | | DONE |
|
|
|
|
Application received | | | 10/2/2013 | | |
|
|
|
|