INSP-Final Inspection | 12/13/2013 | 12/16/2013 | 12/16/2013 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in | 11/29/2013 | 11/29/2013 | 11/29/2013 | P | PART |
Forrest France
|
|
|
C/N items finished. Remainder of overhead rough-in passed inspection including added heads at entry vestibule, branch line restraints, seismic bracing.
|
INSP-Sprinkler Rough-in/Hydro | 11/27/2013 | 11/29/2013 | 11/29/2013 | A | PART |
Forrest France
|
|
|
Overhead hydrostatic testing completed satisfactory.
|
INSP-Sprinkler Rough-in | 11/12/2013 | 11/12/2013 | 11/12/2013 | P | PART |
Troy Cobbley
|
|
|
Re-submitt plans showing the arm-overs on the 2" overhead lines which could affect hydraulic calculations as being more demanding than the existing remote area.. Provide branchline restraints. Provide E.Q. bracing as discussed in the riser room. Provide upright sprinkler head in the entry canopy as discussed. Sprinkler piping in the restrooms is ok to cover and the general installation of the overhead lines is passed.
|
INSP-Conference | 11/7/2013 | 11/8/2013 | 11/8/2013 | A | DONE |
Troy Cobbley
|
|
|
Construction at front entry has changed to combustible. I agreed that a single upright head and as-builts showing this addition would suffice. I noted that four way bracing will be required at the top of the main piping at the risers above the restrooms.
|
Sprinkler Plan Check | 10/29/2013 | | 10/29/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/29/2013 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 10/29/2013 | | DONE |
Barbara Stitt
|
|
|
|
Inspection Record Card- Fire | 10/29/2013 | | 10/29/2013 | | DONE |
Barbara Stitt
|
|
|
|
Issue and Print Permit | | | 10/29/2013 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (Tim) | 10/25/2013 | | 10/25/2013 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 10/25/2013 | | 10/25/2013 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 10/25/2013 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 10/25/2013 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 10/17/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 17 2013 2:44PM
|