INSP-Final Inspection | 2/26/2014 | 2/26/2014 | 2/26/2014 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 2/24/2014 | 2/25/2014 | 2/25/2014 | A | PART |
Forrest France
|
|
|
Light fixtures at the elevator lobby need relocated, need to verifiy upright protection above the room adjacent to the womens restroom.
|
INSP-Final Inspection | 2/20/2014 | 2/21/2014 | 2/21/2014 | A | PART |
Forrest France
|
|
|
Blocked upright head at the SW corner, remove foil at uprights, not all areas accessible for inspection due to flooring install underway.
|
INSP-Final Inspection | 2/19/2014 | 2/20/2014 | 2/20/2014 | P | CANC |
Forrest France
|
|
|
Mike B is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 2/14/2014 | 2/18/2014 | 2/18/2014 | A | PART |
Forrest France
|
|
|
Grid ceiling areas okayed for cover.
|
INSP-Sprinkler Rough-in | 11/8/2013 | 11/12/2013 | 11/12/2013 | P | PART |
Craig D. Hanson
|
|
|
Cover of hard lids. Pass
|
Sprinkler Plan Check | 10/29/2013 | | 10/29/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 10/29/2013 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/29/2013 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 10/29/2013 | | DONE |
Christina Prado
|
|
|
|
Issue and Print Permit | | | 10/29/2013 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 10/29/2013 | | 10/29/2013 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (Tim) | 10/25/2013 | | 10/25/2013 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 10/22/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 22 2013 12:04PM
|