INSP-Final Inspection | 7/15/2014 | 7/16/2014 | 7/17/2014 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 7/14/2014 | 7/15/2014 | 7/15/2014 | P | FAIL |
Troy Cobbley
|
|
|
Provide all signs/tags/stickers for the final and replace the flow switch.
|
INSP-Supply line flush | 7/8/2014 | 7/9/2014 | 7/9/2014 | P | PART |
Forrest France
|
|
|
Completed UG fire supply line flush for buildings 1 and 2.
|
INSP-Sprinkler Rough-in/Hydro | 7/8/2014 | 7/9/2014 | 7/9/2014 | A | PART |
Forrest France
|
|
|
UG fire supply lines passed hydrostatic testing.
|
INSP-Sprinkler Rough-in | 11/12/2013 | 11/12/2013 | 11/12/2013 | P | PASS |
Troy Cobbley
|
|
|
Underground piping is ok to cover.
|
Sprinkler Plan Check | 10/30/2013 | | 10/30/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 10/30/2013 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/30/2013 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 10/30/2013 | | DONE |
Barbara Stitt
|
|
|
|
Inspection Record Card- Fire | 10/30/2013 | | 10/30/2013 | | DONE |
Barbara Stitt
|
|
|
|
Issue and Print Permit | | | 10/30/2013 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (Tim) | 10/29/2013 | | 10/29/2013 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 10/28/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 28 2013 2:19PM
|