Permit NumberFIR13-00609
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 300 S CAPITOL BLVD
Project NameTrader Joe's T.I.
Customer Number 
ePlanReviewYes
Description
The fire sprinkler scope of work consists of adding, plugging and relocating sprinklers to accommodate new wall and ceiling configuration.

To build-out for the first time a new retail tenant in a 13,184 sq. ft. building per approved plans. Shell building done under permit BLD13-00729. Work to include: construction of interior nonbearing walls to divide this space into sales area, storage room, office, two fully accessible restrooms for men/women, prep. room, demo area, break room, and locker room; install a suspended ceiling grid system, drinking fountains, service sink, electrical, mechanical & plumbing; and related interior finishes in compliance with chapter 8 of the 2009 IBC. All work per the approved plans, attached plan review report, and all other reviewing agencies approvals. Energy code compliance for the envelope was part of the SHELL permit. Sealing & insulation of ductwork, mechanical and lighting compliance are a part of this permit. NOTE: This building is required to be fire sprinklered for occupancy & area increase provisions. Any alterations or modifications to the fire sprinkler system shall be per NFPA 13 as regulated by the fire department. A Certificate of Occupancy with the occupant load total is required to be obtained after all work has been inspected and approved and prior to tenant occupying this space. **SRZ**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection1/13/20141/14/20141/14/2014PPASS
DetailsForrest France
Final walkthrough completed satisfactory. Note* missing "wheel" handle at the wall post indicator to be provided prior to building final.
Override - Parcel Holds1/13/20141/1/19001/13/2014  
FIR final only
INSP-Sprinkler Rough-in12/30/20131/2/20141/2/2014APART
DetailsForrest France
Overhead fire sprinkler work at the grid ceiling areas approved for cover.
INSP-Sprinkler Rough-in12/27/201312/31/201312/30/2013ACANC
DetailsForrest France
Nate is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Sprinkler Rough-in12/5/201312/6/201312/18/2013PPART
DetailsForrest France
INSP-Sprinkler Rough-in12/4/201312/5/201312/5/2013PPART
DetailsTroy Cobbley
See the city approved plans for locations of hard lids where sprinkler piping can be covered. I spoke with Nate and the project superintendant about the NON-rated wood that has been installed that will require fire protection. Also a mechanical mezzanine exits that may need additional fire protection in the surrounding areas.
Sprinkler Plan Check11/15/2013 11/15/2013 PASS
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  11/15/2013 DONE
DetailsTim Frost
Permit Ready to Issue  11/15/2013  
Inspection Record Card- Fire11/15/2013 11/15/2013 DONE
DetailsDarla L Downs
Issue and Print Permit  11/15/2013 DONE
Sprinkler Plan Check11/5/2013 11/5/2013 FAIL
DetailsTim Frost
1st review completed  11/5/2013 FAIL
DetailsTim Frost
Miscellaneous action  11/5/2013 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Plan assigned to (Tim)11/4/2013 11/4/2013 DONE
DetailsTim Frost
Application received  11/1/2013 DONE
Application submitted via PDS Online on Nov 1 2013 2:52PM