INSP-Final Inspection | 5/29/2014 | 5/30/2014 | 5/30/2014 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
Miscellaneous action | | | 5/30/2014 | | PASS |
|
|
|
Reviewed as built drawings. Everything was ok but the column protection needs to be installed at 15' not the 12' shown on the drawing.
|
INSP-Final Inspection | 5/21/2014 | 5/22/2014 | 5/22/2014 | P | FAIL |
Troy Cobbley
|
|
|
Provide re-submittals as previously discussed. Forward flush passed and final rough-in inspection for the office area passed.
|
INSP-Sprinkler Rough-in/Hydro | 4/21/2014 | 4/22/2014 | 4/22/2014 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed.
|
INSP-Sprinkler Rough-in | 3/25/2014 | 3/27/2014 | 3/27/2014 | P | PASS |
Troy Cobbley
|
|
|
Overhead rough-in passed. Will need a cover inspection once the pendant heads in the office area are installed. It appears that branchline restraints will be required and the combustible concealed space at the front entrance will need addressed. Mike stated that they are resubmitting showing the column protection and the relocation of the east main (office area).
|
Sprinkler Plan Check | 3/24/2014 | | 3/24/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/24/2014 | | DONE |
Tim Frost
|
|
|
|
CHANGE STATUS TO (ISS) | | | 3/24/2014 | | DONE |
|
|
|
plan mod approved and paid
|
INSP-Supply line flush | 3/20/2014 | 3/21/2014 | 3/21/2014 | P | PART |
Forrest France
|
|
|
UG fire supply line flush completed satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 3/14/2014 | 3/14/2014 | 3/14/2014 | P | PASS |
Troy Cobbley
|
|
|
The ug hydro passed
|
INSP-Sprinkler Rough-in | 2/21/2014 | 2/24/2014 | 2/25/2014 | P | PART |
Forrest France
|
|
|
UG fire supply line including the IBR approved for bury.
|
Permit Ready to Issue | | | 12/26/2013 | | DONE |
Christina Prado
|
|
|
|
Issue and Print Permit | | | 12/26/2013 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 12/26/2013 | | 12/26/2013 | | DONE |
Christina Prado
|
|
|
|
Sprinkler Plan Check | 12/23/2013 | | 12/23/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/23/2013 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 12/9/2013 | | 12/9/2013 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 12/9/2013 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 12/9/2013 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Miscellaneous action | | | 12/6/2013 | | DONE |
|
|
|
Sent the following email to Tom
Tom,
Some of the items were not corrected in the orignal prescreen review.
Additionally,
The owner's certificate provided by Tim Haymes indicates 5-10 pallet loads of f;ammable and combustible liquids, aerosol, compressed gas, and oxiders. The warehouse is obviously capable of storing more than 10 pallet loads. Based on the owner's certificate you originally provided I see a great deal of plastics. At this time I am not convinced this is a class IV warehouse. Please, complete form 606 for each commodity. NOTE: Where it says commodity description provide the commodity and packaging description NOT the commodity classification. The flammable liquids and the other hazardous materials are in small enough quantities they do not appear to cause a problem. However, per IFC 2304.1 the system has to be designed for the worst hazard. Tim Haymes has supplied be with a list of the high hazard materials. What is the remainder being stored? How/Why are you designing for a Class IV? I need more information on the material being stored and the packaging material.
Tim
|
Miscellaneous action | | | 11/19/2013 | | DONE |
|
|
|
Sent the following email to Tom Easton
Tom,
I need an accurately completed Owner’s Certificate (please see attached). I need and accurately completed HMI (Hazardous Material Inventory Statement). I require exact quantities (do not use the words small medium large, etc.) see IFC 407.5, 2701.5.2 Please, complete all items in 2701.5.2 for EACH hazardous material. I have circled a few of the hazardous materials I noticed. I have also enclosed a list of City of Boise approved HMI consultants. There may not be a large enough quantity of a material to pose a problem. However, combined they may be a problem. Until we have exact quantities there is no way to know for certain.
Where is the Idle Pallets being stored (how high)?
Looking over the list of materials, I find it highly dubious the materials contain <25% plastics. Please, verify.
Due to several situations, now and in the future, I require that the Owner’s Certificate be completed by owner, NOT and owner’s representative.
This project will be on hold until I received the above information.
|
Plan assigned to (Tim) | 11/13/2013 | | 11/13/2013 | | DONE |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 11/13/2013 | | 11/13/2013 | | FAIL |
Tim Frost
|
|
|
Failed prescreen
|
Application received | | | 11/6/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 6 2013 9:13AM
|