INSP-Final Inspection | 3/21/2014 | 3/21/2014 | 3/21/2014 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Final Inspection | 3/20/2014 | 3/21/2014 | 3/21/2014 | A | PART |
Forrest France
|
|
|
Completed satisfactory air testing of the new dry system per NFPA 13 within allowable pressure loss at the guage.
|
INSP-Sprinkler Rough-in | 3/20/2014 | 3/20/2014 | 3/20/2014 | P | PASS |
Troy Cobbley
|
|
|
Started 24 hr air test at 10:30 with 52 psi on the guage.
|
INSP-Final Inspection | 3/18/2014 | 3/19/2014 | 3/19/2014 | A | FAIL |
Troy Cobbley
|
|
|
Not ready for a final yet. Overhead hydro passed. Forward flush passed. Trip test of 28 seconds passed. Rough-in inspection for concealed area passed. Missing seismic brace provided. Signal test of tampers and pressure switches passed. Still need the 24 hour air test.
|
INSP-Sprinkler Rough-in | 3/3/2014 | 3/3/2014 | 3/3/2014 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Missing one earth quake brace and need access to the above ceiling areas as discussed.
|
Sprinkler Plan Check | 2/26/2014 | | 2/26/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/26/2014 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 2/26/2014 | | DONE |
Christina Prado
|
|
|
|
CHANGE STATUS TO (ISS) | | | 2/26/2014 | | DONE |
Christina Prado
|
|
|
|
Sprinkler Plan Check | 11/26/2013 | | 11/26/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/26/2013 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 11/26/2013 | | |
|
|
|
|
Inspection Record Card- Fire | 11/26/2013 | | 11/26/2013 | | DONE |
Darla L Downs
|
|
|
|
Issue and Print Permit | | | 11/26/2013 | | DONE |
|
|
|
|
Sprinkler Plan Check | 11/22/2013 | | 11/22/2013 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 11/22/2013 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 11/22/2013 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Miscellaneous action | | | 11/19/2013 | | DONE |
|
|
|
Spoke with Jeff Anderson yesterday. I told him the 606 forms were incomplete. I also asked where the idle pallets will be stored. In addition, I asked him to verify that there is less than 10% plastic in the pallets. This seem highly unlikely due to what Hickory Farms ships.
|
Miscellaneous action | | | 11/14/2013 | | FAIL |
|
|
|
Failed Prescreen,
Waiting on form 606 and what is a storage tote.
|
Plan assigned to (Tim) | 11/13/2013 | | 11/13/2013 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 11/6/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 6 2013 10:51AM
|