INSP-Final Inspection | 8/27/2014 | 8/28/2014 | 8/28/2014 | A | PASS |
Troy Cobbley
|
|
|
24 hour air test passed and earth quake bracing has been added. Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 8/26/2014 | 8/27/2014 | 8/27/2014 | A | PART |
Troy Cobbley
|
|
|
24 hour air test started at 9:00am with pressure marked on guage. Roughin on second pit and piping under equipment passed except it appears a longitudinal bracing is missing on the 3" main.
|
INSP-Sprinkler Rough-in/Hydro | 8/21/2014 | 8/22/2014 | 8/22/2014 | P | PASS |
Troy Cobbley
|
|
|
Overhead 200lb hydro test passed for both systems. Rough-in passed for east garbage/conveyor pit.
|
Sprinkler Plan Check | 8/13/2014 | | 8/13/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/13/2014 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 8/13/2014 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/13/2014 | | DONE |
Candy A. Nichols
|
|
|
|
CHANGE STATUS TO (ISS) | | | 8/13/2014 | | DONE |
Candy A. Nichols
|
|
|
|
INSP-Final Inspection | 5/8/2014 | 5/9/2014 | 5/9/2014 | A | PART |
Troy Cobbley
|
|
|
All corrections have been completed and the forward flush passed. Can not final this permit until possible modifications have been performed due to equipment being installed.
|
INSP-Final Inspection | 5/7/2014 | 5/8/2014 | 5/8/2014 | P | FAIL |
Troy Cobbley
|
|
|
Need forward flush, 911 sticker and zone map to finish. All alarm devices tested ok. Siesmic bracing has been installed.
|
INSP-Sprinkler Rough-in/Hydro | 5/5/2014 | 5/6/2014 | 5/6/2014 | A | PASS |
Troy Cobbley
|
|
|
The 24 hour air test passed for both dry systems.
|
INSP-Sprinkler Rough-in/Hydro | 5/2/2014 | 5/5/2014 | 5/5/2014 | A | PASS |
Troy Cobbley
|
|
|
The 24 hour air test was started at 8:00 am with the pressure guages marked in red for both north and south dry systems.
|
INSP-Sprinkler Rough-in/Hydro | 5/1/2014 | 5/1/2014 | 5/1/2014 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro on all four systems passed.
|
INSP-Supply line flush | 4/28/2014 | 4/29/2014 | 4/29/2014 | P | PASS |
Troy Cobbley
|
|
|
Underground Flush passed. Also performed a rough-in and found that the only real issue other than final inspection items is the lack of seismic bracing on all of the branchlines. Per the plans the piping was to be installed without per the exception of chapter 9 but was run at a lower elevation.
|
INSP-Supply line flush | 4/28/2014 | 4/28/2014 | 4/28/2014 | P | PASS |
Troy Cobbley
|
|
|
Underground hydro passed
|
INSP-Sprinkler Rough-in | 3/27/2014 | 3/28/2014 | 3/28/2014 | P | PASS |
Troy Cobbley
|
|
|
Mens and womens restroom piping is ok to cover. Also piping under the stair landing is ok to cover.
|
INSP-Supply line flush | 11/25/2013 | 11/26/2013 | 11/26/2013 | A | PART |
Craig D. Hanson
|
|
|
Underground rough to cover only, no hydro or flush. pass.
|
Permit Ready to Issue | | | 11/18/2013 | | DONE |
Christina Prado
|
|
|
|
Issue and Print Permit | | | 11/18/2013 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 11/18/2013 | | 11/18/2013 | | DONE |
Christina Prado
|
|
|
|
Sprinkler Plan Check | 11/15/2013 | | 11/15/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 11/15/2013 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/15/2013 | | DONE |
Tim Frost
|
|
|
|
Miscellaneous action | | | 11/14/2013 | | PEND |
|
|
|
Ask Greg for additional information on the business model.
|
Plan assigned to (Tim) | 11/13/2013 | | 11/13/2013 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 11/11/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 11 2013 11:16AM
|