Permit Information
Permit NumberFIR13-00661
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 1520 W STATE ST
Project NameCapital City Family Medicine
Customer Number 
ePlanReviewYes
Description
The fire sprinkler scope of work consists of adding, plugging and relocating sprinklers to accommodate new wall and ceiling configuration.

Fire sprinklers used for building area and story increase. To remodel a 7,330 square foot existing tenant space located on the 1st story of an existing building. This tenant will also expand by 5,964 square feet into the basement and by 3,775 square feet into the 2nd story. This building has an 8,604 square foot basement, an 8,604 square foot 1st story, and an 8,246 square foot 2nd story. Work is to include interior nonbearing walls, upgrades to the basement restrooms to make them accessible to the disabled, a folding partition in the basement, an assembly room in the basement, a sump pump to serve new plumbing fixtures in the basement, a new single user restroom within this tenant space on the 1st story, two new single user restrooms within this tenant space on the 2nd story, millwork, interior doors, suspended acoustical ceilings, gypsum board ceilings, and finishes. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection5/5/20145/5/20145/5/2014PPASS
DetailsForrest France
Fire sprinkler permit work approved for final.
INSP-Final Inspection4/1/20144/1/20144/1/2014APART
DetailsForrest France
Okay to final once project finishes are complete.
INSP-Sprinkler Rough-in3/14/20143/17/20143/17/2014PPART
DetailsForrest France
Verified coverage at the first floor lobby and reception areas post temp construction wall removal.
INSP-Sprinkler Rough-in2/17/20142/18/20142/18/2014APART
DetailsForrest France
Okay to cover overhead fire sprinkler modifications completed to date at the first floor remodel area.
INSP-Sprinkler Rough-in/Hydro2/17/20142/19/20142/17/2014ACANC
DetailsForrest France
This is an oh hydro. Stefan is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Sprinkler Rough-in/Hydro2/14/20142/18/20142/17/2014ACANC
DetailsForrest France
Stefan is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Sprinkler Rough-in/Hydro2/14/20142/14/20142/14/2014PPART
DetailsForrest France
INSP-Sprinkler Rough-in2/10/20142/10/20142/10/2014APART
DetailsForrest France
Exam rooms 1st floor north end okayed for cover.
INSP-Sprinkler Rough-in1/28/20141/28/20141/28/2014PPART
DetailsForrest France
Stefan is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus *1st floor partial insp.
INSP-Final Inspection1/9/20141/9/20141/9/2014PPART
DetailsForrest France
Basement and 2nd floor work completed, final pending remainder of work at the 1st floor.
INSP-Sprinkler Rough-in12/30/201312/31/201312/31/2013APART
DetailsForrest France
Pendent head coverage at the remodel areas basement level completed acceptable- okayed for ceiling cover.
INSP-Sprinkler Rough-in12/30/201312/30/201312/30/2013PPART
DetailsForrest France
Completed inspection for upright coverage at the basement level- noted adjustments necessary between hall 004 and conference room 005.
INSP-Sprinkler Rough-in12/5/201312/6/201312/18/2013PPART
DetailsForrest France
INSP-Sprinkler Rough-in12/12/201312/13/201312/13/2013APART
DetailsForrest France
Okay to cover overhead fire sprinkler work at the second floor grid ceiling areas per the project scope.
INSP-Sprinkler Rough-in12/11/201312/11/201312/12/2013PNR
DetailsForrest France
Stefan is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in12/4/201312/5/201312/6/2013ADEFR
DetailsForrest France
Would it be possible to have this inspection
anywhere from 9-noon. Stefan is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus
Plan assigned to (Tim)11/26/2013 11/26/2013 DONE
DetailsTim Frost
Sprinkler Plan Check11/26/2013 11/26/2013 PASS
DetailsTim Frost
Please, see attached comments.
1st review completed  11/26/2013 PASS
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  11/26/2013 DONE
DetailsTim Frost
Issue and Print Permit  11/26/2013 DONE
Inspection Record Card- Fire11/26/2013 11/26/2013 DONE
DetailsTisha Gallop
Application received  11/20/2013 DONE
Application submitted via PDS Online on Nov 20 2013 10:36AM