Case Summary | | | 8/24/2016 | | DONE |
|
|
|
|
Case Summary | | | 4/4/2014 | | |
|
|
|
|
INSP-Final Inspection | 2/20/2014 | 2/20/2014 | 2/20/2014 | P | PASS |
Forrest France
|
|
|
Fire alarm work passed field testing after corrections and adjustments made while on site.
|
INSP-Final Inspection | 2/18/2014 | 2/19/2014 | 2/19/2014 | P | NR |
Forrest France
|
|
|
Pending FIR14-00097
|
Telephone call | | | 12/6/2013 | | DONE |
Lee G Meredith
|
|
|
Lori, of Alarmco called to inform me that a post indicator valve has been added to the system. She wanted to know if a resubmittal would be required. I informed her that I would not require a resubmittal but would require updated drawings in the form of as builts. The post indicator valve will be monitored on a seperate zone.
|
Permit Ready to Issue | | | 12/3/2013 | | DONE |
Christina Prado
|
|
|
|
Issue and Print Permit | | | 12/3/2013 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 12/3/2013 | | 12/3/2013 | | DONE |
Christina Prado
|
|
|
|
Plan resubmittals received | | | 11/27/2013 | | DONE |
Lee G Meredith
|
|
|
Revised drawings received.
|
Alarm Plan Check | 11/27/2013 | | 11/27/2013 | | PASS |
Lee G Meredith
|
|
|
Plans approved with comments
|
PLANS TAKEN FRONT DESK ALARM | | | 11/27/2013 | | DONE |
Lee G Meredith
|
|
|
Plans approved. ProjectDox updated.
|
1st review completed | | | 11/26/2013 | | FAIL |
Lee G Meredith
|
|
|
1st plan review failed. See review comments.
|
Application received | | | 11/25/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 25 2013 4:24PM
|
Plan assigned to (Lee) | 11/25/2013 | | 11/25/2013 | | DONE |
Lee G Meredith
|
|
|
|