INSP-Final Inspection | 2/7/2014 | 2/7/2014 | 2/7/2014 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 1/22/2014 | 1/22/2014 | 1/22/2014 | P | CANC |
Troy Cobbley
|
|
|
Not ready for final until the ceiling tile has been installed.
|
INSP-Sprinkler Rough-in | 1/22/2014 | 1/22/2014 | 1/22/2014 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed. It was agreed one pendant will be relocated due to light fixture obstructions. Piping can be covered.
|
Plan assigned to (Tim) | 12/30/2013 | | 12/30/2013 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 12/30/2013 | | 12/30/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 12/30/2013 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/30/2013 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 12/30/2013 | | 12/30/2013 | | DONE |
Barbara Stitt
|
|
|
|
Permit Ready to Issue | | | 12/30/2013 | | DONE |
Barbara Stitt
|
|
|
|
Issue and Print Permit | | | 12/30/2013 | | DONE |
Barbara Stitt
|
|
|
|
Application received | | | 12/24/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 24 2013 9:00AM
|