INSP-Final Inspection | 3/3/2014 | 3/4/2014 | 3/4/2014 | A | PASS |
Forrest France
|
|
|
Previous C/N items verified for completion. Final walkthrough passed. Fire sprinkler permit finaled.
|
INSP-Final Inspection | 2/27/2014 | 3/3/2014 | 3/3/2014 | P | NH |
Forrest France
|
|
|
Final pending jobsite access.
|
INSP-Sprinkler Rough-in/Hydro | 2/11/2014 | 2/12/2014 | 2/12/2014 | P | PART |
Forrest France
|
|
|
Provide quick response SW heads at four locations below overhead doors, noted two uprights at the SW corner not yet changed to QR. Final pending corrections, escutcheons and project finishes.
|
Sprinkler Plan Check | 1/16/2014 | | 1/16/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/16/2014 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 1/16/2014 | | DONE |
Barbara Stitt
|
|
|
|
Issue and Print Permit | | | 1/16/2014 | | DONE |
Barbara Stitt
|
|
|
|
Inspection Record Card- Fire | 1/16/2014 | | 1/16/2014 | | DONE |
Barbara Stitt
|
|
|
|
Sprinkler Plan Check | 1/15/2014 | | 1/15/2014 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 1/15/2014 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 1/15/2014 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Plan assigned to (Tim) | 1/14/2014 | | 1/14/2014 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 1/10/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 10 2014 1:50PM
|