Case Summary | | | 2/2/2015 | | |
|
|
|
|
DOC - Permit Finaled | | | 2/2/2015 | | DONE |
Christina Prado
|
|
|
Status changed by mistake - see inspection notes from 11/12/14
|
INSP-Final Inspection | 11/12/2014 | 11/12/2014 | 11/12/2014 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 11/7/2014 | 11/10/2014 | 11/10/2014 | A | FAIL |
Troy Cobbley
|
|
|
Flow switch tested/passed. Duct smoke detectors still have issues.
|
INSP-Alarm Testing | 11/6/2014 | 11/7/2014 | 11/7/2014 | A | CANC |
Troy Cobbley
|
|
|
Before 11 - Dale Phone #: ###-####
|
INSP-Final Inspection | 11/5/2014 | 11/6/2014 | 11/6/2014 | A | CANC |
Forrest France
|
|
|
Dale-please call with a meet time Phone #: ###-####
|
Plan resubmittals received | | | 10/31/2014 | | DONE |
|
|
|
|
Alarm Plan Check | 10/31/2014 | | 10/31/2014 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 10/31/2014 | | DONE |
|
|
|
Plan mod approved. Plans taken to front desk for processing.
|
INSP-Alarm Testing | 7/9/2014 | 7/21/2014 | 7/21/2014 | A | DONE |
Troy Cobbley
|
|
|
The existing duct smoke detectors did not shut down upon detection of smoke. The new duct smoke detectors are not connected to the fire alarm panel. Need the correct orfice in the inspectors test line so that the flow switch can be tested. All other items tested ok.
|
Permit Ready to Issue | | | 1/24/2014 | | DONE |
Barbara Stitt
|
|
|
|
Issue and Print Permit | | | 1/24/2014 | | DONE |
Barbara Stitt
|
|
|
|
Inspection Record Card- Fire | 1/24/2014 | | 1/24/2014 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (Lee) | 1/23/2014 | | 1/23/2014 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 1/23/2014 | | PASS |
|
|
|
|
Alarm Plan Check | 1/23/2014 | | 1/23/2014 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 1/23/2014 | | DONE |
|
|
|
Plans approved. ProjectDox updated.
|
Application received | | | 1/22/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 22 2014 2:10PM
|