Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberFIR14-00068
StatusFinaled
Name PHOENIX FIRE PROTECTION
Site Address 5301 E WARM SPRINGS AVE
Project NameThe Terraces Main Bldg
Customer NumberUDG ONLY
ePlanReviewYes
Description
The fire sprinkler scope of work consists of 6”x20± C-900 underground piping with a yard PIV.

Plan Mod #1 – 11/25/2014
Revised underground layout

The Terraces of Boise - Main Building Wing H - To construct a new 66,075 square foot, four story, concrete and steel framed assisted living and memory care and commons building. This is a wing of a larger building, with wings separated by two-hour fire walls. This building is fully fire sprinklered. The sprinklers are used for area increase. First Floor: 7,090 sq. ft. consisting of Commons areas. The commons area contains administrative offices and employee back of house areas. Second Floor: 25,155 sq. ft. with 24 memory care apartments and a dining/living area, kitchen, family room and activity areas. Third Floor: 16,915 sq. ft. with 20 assisted living apartments with a 4,280 sq. ft. occupied landscaped roof area. Fourth Floor: 16,915 sq. ft. with 20 assisted living apartments. All floors contain mechanical/electrical and housekeeping areas. The first and second floor commons areas, on the east side of Wing H, will be constructed as part of Phase I and the memory care and assisted living portion of Wing H will be constructed as part of Phase II. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection11/3/201511/3/201511/3/2015PPASS
DetailsJim Page
PIV tampers in place/operational, underground final inspection passed/complete
INSP-Final Inspection5/29/20156/1/20156/1/2015PCANC
DetailsThomas Walsh
Final signoff on FSUG cannot be granted until fire alarm system interface components, including tampers and waterflows, can be completed.
INSP-Sprinkler Rough-in/Hydro5/26/20155/27/20155/27/2015APASS
DetailsThomas Walsh
Hydrotest of FSUG from city connection to pump room stub up. 200 psi at 2 hours - PASSED
INSP-Supply line flush2/13/20152/13/20152/13/2015PPART
DetailsForrest France
UG fire supply line flush completed
Sprinkler Plan Check11/25/2014 11/25/2014 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  11/25/2014 DONE
DetailsTim Frost
CHANGE STATUS TO (ISS)  11/25/2014 DONE
DetailsCandy A. Nichols
INSP-Sprinkler Rough-in9/19/20149/22/20149/22/2014PPART
DetailsForrest France
Completed inspection for remainder of UG fire supply line to the point of connection. * Note: Field install does not match approved plans- two 45's have been added and the PIV as shown has been deleted. Need to provide a plan modification prior to final. Verified thrust blocking, tracer, piping, bury depth, etc.
INSP-Sprinkler Rough-in/Hydro5/6/20145/6/20145/6/2014APART
DetailsForrest France
Verified ductile riser, thrust block, tracer and approx. 10' stub out for the UG fire supply line east side. Need to ensure bedding per NFPA standards.
Sprinkler Plan Check3/26/2014 3/26/2014 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  3/26/2014 DONE
DetailsTim Frost
Permit Ready to Issue  3/26/2014 DONE
Issue and Print Permit  3/26/2014 DONE
Inspection Record Card- Fire3/26/2014 3/26/2014 DONE
DetailsTisha Gallop
Sprinkler Plan Check2/19/2014 2/19/2014 FAIL
DetailsTim Frost
Miscellaneous action  2/19/2014 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Plan assigned to (Tim)2/12/2014 2/12/2014 DONE
DetailsTim Frost
Sprinkler Plan Check2/12/2014 2/12/2014 FAIL
DetailsTim Frost
1st review completed  2/12/2014 FAIL
DetailsTim Frost
Miscellaneous action  2/12/2014 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Application received  1/28/2014 DONE
Application submitted via PDS Online on Jan 28 2014 3:30PM