INSP-Final Inspection | 11/3/2015 | 11/3/2015 | 11/3/2015 | P | PASS |
Jim Page
|
|
|
PIV tampers in place/operational, underground final inspection passed/complete
|
INSP-Final Inspection | 5/29/2015 | 6/1/2015 | 6/1/2015 | P | CANC |
Thomas Walsh
|
|
|
Final signoff on FSUG cannot be granted until fire alarm system interface components, including tampers and waterflows, can be completed.
|
INSP-Sprinkler Rough-in/Hydro | 5/26/2015 | 5/27/2015 | 5/27/2015 | A | PASS |
Thomas Walsh
|
|
|
Hydrotest of FSUG from city connection to pump room stub up. 200 psi at 2 hours - PASSED
|
INSP-Supply line flush | 2/13/2015 | 2/13/2015 | 2/13/2015 | P | PART |
Forrest France
|
|
|
UG fire supply line flush completed
|
Sprinkler Plan Check | 11/25/2014 | | 11/25/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/25/2014 | | DONE |
Tim Frost
|
|
|
|
CHANGE STATUS TO (ISS) | | | 11/25/2014 | | DONE |
Candy A. Nichols
|
|
|
|
INSP-Sprinkler Rough-in | 9/19/2014 | 9/22/2014 | 9/22/2014 | P | PART |
Forrest France
|
|
|
Completed inspection for remainder of UG fire supply line to the point of connection. * Note: Field install does not match approved plans- two 45's have been added and the PIV as shown has been deleted. Need to provide a plan modification prior to final. Verified thrust blocking, tracer, piping, bury depth, etc.
|
INSP-Sprinkler Rough-in/Hydro | 5/6/2014 | 5/6/2014 | 5/6/2014 | A | PART |
Forrest France
|
|
|
Verified ductile riser, thrust block, tracer and approx. 10' stub out for the UG fire supply line east side. Need to ensure bedding per NFPA standards.
|
Sprinkler Plan Check | 3/26/2014 | | 3/26/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/26/2014 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 3/26/2014 | | DONE |
|
|
|
|
Issue and Print Permit | | | 3/26/2014 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/26/2014 | | 3/26/2014 | | DONE |
Tisha Gallop
|
|
|
|
Sprinkler Plan Check | 2/19/2014 | | 2/19/2014 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 2/19/2014 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Plan assigned to (Tim) | 2/12/2014 | | 2/12/2014 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 2/12/2014 | | 2/12/2014 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 2/12/2014 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 2/12/2014 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 1/28/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 28 2014 3:30PM
|