INSP-Final Inspection | 4/1/2014 | 4/2/2014 | 4/2/2014 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 3/20/2014 | 3/24/2014 | 3/24/2014 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro test of the pre-action system passed. Rough-in passed. Piping can be covered.
|
INSP-Sprinkler Rough-in/Hydro | 3/19/2014 | 3/20/2014 | 3/20/2014 | A | CANC |
Troy Cobbley
|
|
|
Cancel per sam and brian
|
Plan assigned to (Tim) | 2/24/2014 | | 2/24/2014 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 2/24/2014 | | 2/24/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 2/24/2014 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/24/2014 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 2/24/2014 | | DONE |
Christina Prado
|
|
|
|
Issue and Print Permit | | | 2/24/2014 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 2/24/2014 | | 2/24/2014 | | DONE |
Christina Prado
|
|
|
|
Application received | | | 2/21/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 21 2014 11:22AM
|