INSP-Final Inspection | 4/2/2014 | 4/2/2014 | 4/2/2014 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 3/31/2014 | 4/1/2014 | 4/1/2014 | A | FAIL |
Troy Cobbley
|
|
|
Need to add strobe coverage at the "man trap". Agreed to test all devices when that change is made.
|
Permit Ready to Issue | | | 3/6/2014 | | DONE |
Christina Prado
|
|
|
|
Issue and Print Permit | | | 3/6/2014 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 3/6/2014 | | 3/6/2014 | | DONE |
Christina Prado
|
|
|
|
Plan resubmittals received | | | 3/5/2014 | | DONE |
|
|
|
|
Alarm Plan Check | 3/5/2014 | | 3/5/2014 | | PASS |
Lee G Meredith
|
|
|
|
1st review completed | | | 3/5/2014 | | PASS |
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 3/5/2014 | | DONE |
|
|
|
Plan approved. ProjectDox updated.
|
Miscellaneous action | | | 3/3/2014 | | DONE |
|
|
|
Failed initial submittal on prescreen review. Missing all load calculations.
|
Plan assigned to (Lee) | 2/27/2014 | | 2/27/2014 | | DONE |
Lee G Meredith
|
|
|
|
Miscellaneous action | | | 2/27/2014 | | DONE |
|
|
|
Emailed Dante to let him know that one form in the documents folder is corrupt and can't be read. Also informed him that there are no NAC calculations provided.
|
Application received | | | 2/26/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 26 2014 2:02PM
|