INSP-Final Inspection | 9/25/2014 | 9/26/2014 | 9/26/2014 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 9/10/2014 | 9/11/2014 | 9/11/2014 | A | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed
|
INSP-Supply line flush | 9/10/2014 | 9/10/2014 | 9/10/2014 | P | PASS |
Troy Cobbley
|
|
|
Underground flush passed
|
INSP-Sprinkler Rough-in | 8/7/2014 | 8/8/2014 | 8/8/2014 | A | PASS |
Troy Cobbley
|
|
|
Remaining underground supply piping is ok to cover.
|
INSP-Sprinkler Rough-in | 4/17/2014 | 4/23/2014 | 4/23/2014 | A | PART |
Forrest France
|
|
|
UG fire supply line ductile riser piece and 6" C-900 stub out to a point 8' beyond the stem wall okay for bury.
|
INSP-Sprinkler Rough-in | 4/15/2014 | 4/16/2014 | 4/16/2014 | A | CANC |
Troy Cobbley
|
|
|
cancel per Trent
|
Permit Ready to Issue | | | 4/10/2014 | | DONE |
Christina Prado
|
|
|
|
Issue and Print Permit | | | 4/10/2014 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 4/10/2014 | | 4/10/2014 | | DONE |
Christina Prado
|
|
|
|
Sprinkler Plan Check | 4/9/2014 | | 4/9/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/9/2014 | | DONE |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 3/31/2014 | | 3/31/2014 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 3/31/2014 | | 3/31/2014 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 3/31/2014 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 3/31/2014 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 3/26/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 26 2014 4:41PM
|