INSP-Final Inspection | 7/8/2014 | 7/11/2014 | 7/11/2014 | A | PASS |
Forrest France
|
|
|
Scope of fire sprinkler work passed final walkthrough.
|
INSP-Final Inspection | 7/1/2014 | 7/2/2014 | 7/2/2014 | P | PART |
Forrest France
|
|
|
Walkthrough completed for the 2nd floor meeting room fire sprinkler finish work.
|
INSP-Sprinkler Rough-in | 6/10/2014 | 6/11/2014 | 6/11/2014 | A | PART |
Forrest France
|
|
|
Okayed remainder of overhead work at the future meeting rooms 2nd floor per the scope of work indicated on approved plans. Drop ceilings okay for cover.
|
INSP-Sprinkler Rough-in | 6/4/2014 | 6/5/2014 | 6/5/2014 | A | PART |
Forrest France
|
|
|
Okay to cover fire sprinkler work at the sheetrock ceilings and soffits as marked on approved plans in the meeting room areas 2nd floor east side.
|
INSP-Sprinkler Rough-in | 6/4/2014 | 6/4/2014 | 6/4/2014 | P | PART |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in | 5/12/2014 | 5/13/2014 | 5/13/2014 | A | PART |
Forrest France
|
|
|
Verified seismic restraint at four locations west side.
|
Permit Ready to Issue | | | 4/21/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Issue and Print Permit | | | 4/21/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Inspection Record Card- Fire | 4/21/2014 | | 4/21/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Sprinkler Plan Check | 4/18/2014 | | 4/18/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/18/2014 | | DONE |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 4/16/2014 | | 4/16/2014 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 4/16/2014 | | 4/16/2014 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 4/16/2014 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 4/16/2014 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 4/14/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 14 2014 1:03PM
|