INSP-Final Inspection | 8/29/2014 | 9/2/2014 | 9/2/2014 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 8/29/2014 | 8/29/2014 | 8/29/2014 | P | CANC |
Troy Cobbley
|
|
|
Cancel per Tom Phone #: ###-####
|
INSP-Final Inspection | 8/28/2014 | 8/28/2014 | 8/28/2014 | P | CANC |
Troy Cobbley
|
|
|
Cancel per Tom
|
INSP-Sprinkler Rough-in | 6/23/2014 | 6/24/2014 | 6/24/2014 | P | PASS |
Troy Cobbley
|
|
|
24 hour air test passed. All piping can be covered. Rough-in passed for the front and rear canopies.
|
INSP-Sprinkler Rough-in | 6/23/2014 | 6/23/2014 | 6/23/2014 | P | PART |
Troy Cobbley
|
|
|
24 hour air test started at 12:30 with 44 psi
|
INSP-Sprinkler Rough-in/Hydro | 6/18/2014 | 6/19/2014 | 6/19/2014 | A | PASS |
Troy Cobbley
|
|
|
Overhead dry system hydro test passed.
|
INSP-Sprinkler Rough-in | 6/5/2014 | 6/5/2014 | 6/5/2014 | P | PASS |
Troy Cobbley
|
|
|
Overbuild/combustible concealed area sprinkler rough-in passed.
|
Permit Ready to Issue | | | 5/5/2014 | | DONE |
Christina Prado
|
|
|
|
Issue and Print Permit | | | 5/5/2014 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 5/5/2014 | | 5/5/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (Tim) | 5/2/2014 | | 5/2/2014 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 5/2/2014 | | 5/2/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 5/2/2014 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/2/2014 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 4/28/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 28 2014 3:02PM
|