Case Summary | | | 2/2/2015 | | |
|
|
|
|
INSP-Final Inspection | 6/2/2014 | 6/13/2014 | 6/13/2014 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. Netcon was 5.
|
Permit Ready to Issue | | | 5/14/2014 | | DONE |
|
|
|
|
Issue and Print Permit | | | 5/14/2014 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 5/14/2014 | | 5/14/2014 | | DONE |
Christina Prado
|
|
|
|
Miscellaneous action | | | 5/9/2014 | | DONE |
|
|
|
This is the first electronic application for this customer after years of paper submittals. After several emails back and forth with the applicant, we were finally able to come up with a submittal that met the basic requirements.
|
Alarm Plan Check | 5/9/2014 | | 5/9/2014 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 5/9/2014 | | DONE |
|
|
|
Plans approved with review comments and conditions. Projectdox updated.
|
Application received | | | 5/6/2014 | | DONE |
|
|
|
Application submitted via PDS Online on May 6 2014 10:26AM
|
Plan assigned to (Lee) | 5/6/2014 | | 5/6/2014 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 5/6/2014 | | FAIL |
|
|
|
|