FA submittal on Garage#1 consists on complete notification system, sprinkler monitoring and elevators interface. FACp to be located at the 1st floor Wing C, the FACT will be provisory until the final the entire complex and converted later on to a transponder, tie to the main FACP. Associated with building permit BLD13-00179.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection6/12/20156/12/20156/12/2015APASS
DetailsThomas Walsh
Final inspection of fire alarm components for the garage level of Wings A,B,C and D, including all initiating devices, including MPs, elevator recall functions, SFDs, notification devices, etc
INSP-Alarm Testing6/8/20156/8/20156/8/2015PPART
DetailsThomas Walsh
Inspection/ test of fire alarm system for the permit coverage area, including manual pulls, smoke detection, waterflows, tamper supervisories, and audibility/visual device testing.
NOTE: No FSDs or elevator functions tested this visit.
Permit Ready to Issue  5/19/2014 DONE
DetailsChristina Prado
Issue and Print Permit  5/19/2014 DONE
DetailsChristina Prado
Inspection Record Card- Fire5/19/2014 5/19/2014 DONE
DetailsChristina Prado
PLANS TAKEN FRONT DESK ALARM  5/16/2014 DONE
Pleans approved with review comments. Projectdox updated.
Alarm Plan Check5/15/2014 5/15/2014 PASS
DetailsLee G Meredith
Plan resubmittals received  5/14/2014 DONE
Meeting  5/12/2014 DONE
Dante and I met today with a reduced size set of drawings. We discussed and noted the need to eliminate information from the drawings that was not part of the current phase of work. Dante agreed to resubmit drawings with clearer definition of the specific phase of work associated with the permit at hand.
1st review completed  5/12/2014 FAIL
Plans failed in prescreen review. Current submittal has all 3 phases of construction included in the initial submittal. This makes it difficult to determine the actual work. Dante is going to resubmit drawings in a manner that clearly deliniates the actual wok for the specific phase at hand. As permits are applied for, additional - phase related information will be added.
Plan assigned to (Lee)5/9/2014 5/9/2014 DONE
DetailsLee G Meredith
Telephone call  5/9/2014 DONE
Dante submitted all 3 phases on this multi phased project but had not clearly identified the specific portion of the drawings that identify this phase (1) of the project. We discussed the difficulties this was presenting for review and inspection of the project via telephone call. Dante is going to bring in a set of drawings next week and we will review how it needs to be revised to clearly indicate the scope of work for each phase.
Application received  5/7/2014 DONE
Application submitted via PDS Online on May 7 2014 2:46PM