INSP-Final Inspection | 8/7/2014 | 8/8/2014 | 8/7/2014 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in | 7/31/2014 | 8/1/2014 | 8/1/2014 | A | PART |
Troy Cobbley
|
|
|
1st floor Quail Court Rough In passed and piping can be covered. One problem is there has been non-rated wood installed above the ceiling assembly that will need to be addressed prior to a final sign off. I spoke to Clarence and John about this problem.
|
INSP-Final Inspection | 7/21/2014 | 7/21/2014 | 7/21/2014 | P | PART |
Troy Cobbley
|
|
|
2nd floor only fire sprinkler work is complete
|
INSP-Sprinkler Rough-in | 6/24/2014 | 6/25/2014 | 6/25/2014 | P | PART |
Forrest France
|
|
|
Second floor fire sprinkler work passed cover inspection with the exception of one overspaced area in the corridor. Also noted one damaged head to be replaced. Locations marked and dated on approved plans.
|
INSP-Sprinkler Rough-in | 6/24/2014 | 6/24/2014 | 6/24/2014 | P | CANC |
Troy Cobbley
|
|
|
Need the inspection latest as possible. partial Rough in for 2nd floor only. James is fitter onsite. if you cant get him call John at ###-#### Phone #: ###-#### >> Inspection requested via web by John Venche Inspection cancelled from web by: John Venche
|
Sprinkler Plan Check | 5/19/2014 | | 5/19/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/19/2014 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 5/19/2014 | | DONE |
|
|
|
|
Issue and Print Permit | | | 5/19/2014 | | |
|
|
|
|
Inspection Record Card- Fire | 5/19/2014 | | 5/19/2014 | | DONE |
Tisha Gallop
|
|
|
|
Sprinkler Plan Check | 5/15/2014 | | 5/15/2014 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 5/15/2014 | | FAIL |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 5/14/2014 | | 5/14/2014 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 5/9/2014 | | DONE |
|
|
|
Application submitted via PDS Online on May 9 2014 8:10AM
|