INSP-Final Inspection | 10/23/2014 | 10/24/2014 | 10/23/2014 | A | PASS |
Forrest France
|
|
|
Okay for final status per C. Hanson.
|
INSP-Sprinkler Rough-in | 5/20/2014 | 5/20/2014 | 5/20/2014 | P | PART |
Forrest France
|
|
|
Installation appears acceptable however the piping material and routing has changed from the approved plan.- ( Pipe as installed is sch. 80 PVC, service location is now on the opposite side of the property). Plan modification will be necessary prior to permit final.
|
Plan assigned to (Tim) | 5/19/2014 | | 5/19/2014 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 5/19/2014 | | 5/19/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 5/19/2014 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/19/2014 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 5/19/2014 | | DONE |
Christina Prado
|
|
|
|
Issue and Print Permit | | | 5/19/2014 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 5/19/2014 | | 5/19/2014 | | DONE |
Christina Prado
|
|
|
|
Application received | | | 5/16/2014 | | DONE |
|
|
|
Application submitted via PDS Online on May 16 2014 3:18PM
|