INSP-Final Inspection | 9/16/2014 | 9/17/2014 | 9/17/2014 | A | PASS |
Forrest France
|
|
|
Verified additional coverage at new overhead door. Final walkthrough completed. Fire sprinkler permit finaled.
|
INSP-Sprinkler Rough-in | 8/27/2014 | 8/28/2014 | 8/28/2014 | A | PART |
Forrest France
|
|
|
Okay to cover overhead work at the grid ceiling areas per the scope of remodel. * Noted a new overhead door at the back of warehouse- provide additional sprinkler coverage at this location.
|
Sprinkler Plan Check | 8/8/2014 | | 8/8/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/8/2014 | | DONE |
Tim Frost
|
|
|
|
CHANGE STATUS TO (ISS) | | | 8/8/2014 | | DONE |
Barbara Stitt
|
|
|
|
Inspection Record Card- Fire | 8/8/2014 | | 8/8/2014 | | DONE |
Barbara Stitt
|
|
|
|
(F) Reprint permit | | | 8/8/2014 | | DONE |
Barbara Stitt
|
|
|
|
Sprinkler Plan Check | 6/4/2014 | | 6/4/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/4/2014 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 6/4/2014 | | DONE |
Barbara Stitt
|
|
|
|
Issue and Print Permit | | | 6/4/2014 | | DONE |
Barbara Stitt
|
|
|
|
Inspection Record Card- Fire | 6/4/2014 | | 6/4/2014 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (Tim) | 6/2/2014 | | 6/2/2014 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 6/2/2014 | | 6/2/2014 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 6/2/2014 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 6/2/2014 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 5/29/2014 | | DONE |
|
|
|
Application submitted via PDS Online on May 29 2014 12:56PM
|