INSP-Final Inspection | 11/21/2014 | 11/24/2014 | 11/24/2014 | A | PASS |
Forrest France
|
|
|
Scope of fire sprinkler work at the new lab completed. Mains and branchlines extending to the next phase are installed, however drop ceilings and pendent heads are not yet provided.
|
INSP-Final Inspection | 11/19/2014 | 11/20/2014 | 11/20/2014 | A | CANC |
Forrest France
|
|
|
Please meet in B.25 plan review room Phone #: ###-#### >> Inspection requested via web by John Wheeler Inspection cancelled from web by: John Wheeler
|
Sprinkler Plan Check | 11/6/2014 | | 11/6/2014 | | DONE |
Tim Frost
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 10/8/2014 | 10/9/2014 | 10/9/2014 | A | PART |
Forrest France
|
|
|
Overhead rough-in completed. Need to provide additional coverage at the open area adjacent to the QRA tech room. Drops and sprinklers are not yet installed. Initial hydrostatic test also completed.
|
CHANGE STATUS TO (ISS) | | | 10/8/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (Tim) | 8/28/2014 | | 8/28/2014 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 8/28/2014 | | 8/28/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/28/2014 | | DONE |
Tim Frost
|
|
|
|
Issue and Print Permit | | | 7/29/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Permit Ready to Issue | | | 7/28/2014 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/28/2014 | | 7/28/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (Tim) | 7/18/2014 | | 7/26/2014 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 7/26/2014 | | 7/26/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 7/26/2014 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/26/2014 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 5/29/2014 | | DONE |
|
|
|
This permit was created on the web by Paul Marcolina
|