INSP-Final Inspection | 9/19/2014 | 9/22/2014 | 9/22/2014 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled.
|
INSP-Sprinkler Rough-in | 9/9/2014 | 9/10/2014 | 9/10/2014 | P | PASS |
Troy Cobbley
|
|
|
24 hour air test passed
|
INSP-Sprinkler Rough-in | 9/9/2014 | 9/9/2014 | 9/9/2014 | P | PASS |
Troy Cobbley
|
|
|
24 hour air test started at 1:00 with 44 1/2 psi on the guage
|
INSP-Sprinkler Rough-in/Hydro | 9/8/2014 | 9/9/2014 | 9/9/2014 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro test for the canopy passed.
|
INSP-Sprinkler Rough-in/Hydro | 9/3/2014 | 9/4/2014 | 9/4/2014 | A | CANC |
Troy Cobbley
|
|
|
Cancel per John Phone #: ###-####
|
INSP-Sprinkler Rough-in | 8/18/2014 | 8/18/2014 | 8/18/2014 | P | PASS |
Troy Cobbley
|
|
|
Piping under the canopy is ok to cover. Some of the exposed mains have not been installed yet.
|
Plan assigned to (Tim) | 6/16/2014 | | 6/16/2014 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 6/16/2014 | | 6/16/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 6/16/2014 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/16/2014 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 6/16/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Issue and Print Permit | | | 6/16/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Inspection Record Card- Fire | 6/16/2014 | | 6/16/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Application received | | | 6/4/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 4 2014 2:47PM
|