INSP-Final Inspection | 8/4/2014 | 8/6/2014 | 8/6/2014 | A | PASS |
|
|
|
System tested and pass
|
INSP-Supply line flush | 7/22/2014 | 7/23/2014 | 7/23/2014 | A | PASS |
Troy Cobbley
|
|
|
Underground supply line flush passed
|
INSP-Sprinkler Rough-in | 6/25/2014 | 6/25/2014 | 6/27/2014 | P | PART |
Forrest France
|
|
|
Okay to cover overhead fire sprinkler work. Tenting 2nd floor okayed. Need to provide intermediate temp heads at the furnace closets.
|
INSP-Sprinkler Rough-in/Hydro | 6/24/2014 | 6/25/2014 | 6/25/2014 | A | PART |
Forrest France
|
|
|
OH hydrostatic test completed satisfactory. Tenting needs adjusted at the second floor south apt.
|
Permit Ready to Issue | | | 6/23/2014 | | DONE |
Christina Prado
|
|
|
|
Issue and Print Permit | | | 6/23/2014 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 6/23/2014 | | 6/23/2014 | | DONE |
Christina Prado
|
|
|
|
Sprinkler Plan Check | 6/20/2014 | | 6/20/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/20/2014 | | DONE |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 6/16/2014 | | 6/16/2014 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 6/16/2014 | | 6/16/2014 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 6/16/2014 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 6/16/2014 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 6/7/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 7 2014 2:30PM
|