INSP-Final Inspection | 10/6/2014 | 10/6/2014 | 10/6/2014 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 10/1/2014 | 10/2/2014 | 10/2/2014 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed
|
INSP-Supply line flush | 9/30/2014 | 10/1/2014 | 10/1/2014 | P | PASS |
Troy Cobbley
|
|
|
Underground supply line flush passed
|
INSP-Sprinkler Rough-in | 9/18/2014 | 9/18/2014 | 9/18/2014 | P | CANC |
Troy Cobbley
|
|
|
Brandon-underground flushing Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 9/16/2014 | 9/17/2014 | 9/17/2014 | P | CANC |
Troy Cobbley
|
|
|
Underground hydro - Brandon Phone #: ###-####
|
INSP-Sprinkler Rough-in | 9/4/2014 | 9/4/2014 | 9/4/2014 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Tenting passed. Piping can be covered.
|
INSP-Sprinkler Rough-in | 9/3/2014 | 9/4/2014 | 9/4/2014 | A | PASS |
Troy Cobbley
|
|
|
Piping can be covered.
|
INSP-Sprinkler Rough-in | 8/29/2014 | 8/29/2014 | 8/29/2014 | P | PASS |
Troy Cobbley
|
|
|
Piping rough-in passed. Piping can not be covered until the tenting has been corrected.
|
INSP-Sprinkler Rough-in/Hydro | 8/29/2014 | 8/29/2014 | 8/29/2014 | P | CANC |
Troy Cobbley
|
|
|
Riser is not built yet so not ready for hydro test. Will be rescheduled.
|
INSP-Sprinkler Rough-in | 7/9/2014 | 7/9/2014 | 7/9/2014 | P | PASS |
Troy Cobbley
|
|
|
Underground supply piping is ok to cover.
|
Sprinkler Plan Check | 6/27/2014 | | 6/27/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/27/2014 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 6/27/2014 | | DONE |
|
|
|
|
Issue and Print Permit | | | 6/27/2014 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/27/2014 | | 6/27/2014 | | DONE |
Tisha Gallop
|
|
|
|
Sprinkler Plan Check | 6/18/2014 | | 6/18/2014 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 6/18/2014 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 6/18/2014 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Plan assigned to (Tim) | 6/17/2014 | | 6/17/2014 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 6/10/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 10 2014 8:00AM
|