Information based on query as of Wednesday, August 14, 2024.
Permit Information
Permit NumberFIR14-00358
StatusFinaled
Name ABSOLUTE FIRE PROTECTION
Site Address 646 N FIVE MILE RD
Project NameCradle Point Expansion
Customer Number 
ePlanReviewYes
Description
The fire sprinkler scope of work consists of adding, plugging and relocating sprinklers to accommodate new wall and ceiling configuration.

(CRADLEPOINT) Plan modification to change floor plan to allow for more square footage of F1 occupancy and reduce the S1 occupancy equally. The new demising wall will be routed around the existing fire riser. A wall will be added and removed in the existing break room and 2 existing walls around the production room will be removed to open the space. The ceiling grid will be repaired in these areas. 5-5-14 ajs.This permit is to expand the current occupant into the adjoining tenant space. The site plan indicates the space being reduced in size is currently vacant. Prior to occupancy the tenant shall submit for a building permit for the new square footage and use of the tenant space. Scope of work to include opening in existing 1 hour rated wall, new 1 hour rated tenant demising wall, new exterior opening and roll up door. Plans indicate no racking over 8 feet will be installed. Existing building plan under BLD00-00439. Any racking over 8 feet in height requires a separate racking permit. This building was built under BLD00-00439. NOTE: This building is fully fire sprinklered for area increase. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **ajs**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection7/9/20147/10/20147/10/2014PPASS
DetailsTroy Cobbley
permit finaled
INSP-Sprinkler Rough-in6/30/20147/1/20147/1/2014APASS
DetailsTroy Cobbley
Need sprinkler protection under the south facing overhead door and siesmic restraints on the new branchlines
Permit Ready to Issue  6/19/2014 DONE
DetailsChristina Prado
Issue and Print Permit  6/19/2014 DONE
DetailsChristina Prado
Inspection Record Card- Fire6/19/2014 6/19/2014 DONE
DetailsChristina Prado
Plan assigned to (Tim)6/18/2014 6/18/2014 DONE
DetailsTim Frost
Sprinkler Plan Check6/18/2014 6/18/2014 PASS
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  6/18/2014 DONE
DetailsTim Frost
1st review completed  6/18/2014 PASS
DetailsTim Frost
Application received  6/10/2014 DONE
Application submitted via PDS Online on Jun 10 2014 11:53AM