INSP-Final Inspection | 11/7/2014 | 11/10/2014 | 11/10/2014 | A | PASS |
Forrest France
|
|
|
Fire sprinkler work passed final inspection. Missing escutcheon installed while on site. Surface mounted lights at the utility room adjacent to the garage to be turned 90deg to avoid obstruction to sprinkler coverage as discussed.
|
INSP-Sprinkler Rough-in | 9/4/2014 | 9/4/2014 | 9/5/2014 | P | PART |
Forrest France
|
|
|
Inspection for tenting completed okay after adjustments made while on site at one area 1st floor and 4 locations 2nd floor.
|
INSP-Sprinkler Rough-in/Hydro | 9/3/2014 | 9/4/2014 | 9/4/2014 | A | PART |
Forrest France
|
|
|
UG fire supply line flush completed satisfactory.
|
INSP-Sprinkler Rough-in | 8/22/2014 | 8/22/2014 | 8/22/2014 | A | PART |
Troy Cobbley
|
|
|
The rough-in for the most part is passed. One pendant in the master bath needs to be relocated and plan modifications are needed to be submitted due to new riser location and minor pipe re-routing. Tenting has not been completed yet so no piping can be covered.
|
INSP-Sprinkler Rough-in | 8/21/2014 | 8/21/2014 | 8/22/2014 | P | CANC |
Troy Cobbley
|
|
|
Rescheduled for tomorrow. Johnathon Phone #: ###-####
|
Miscellaneous action | | | 8/22/2014 | | DONE |
|
|
|
Evaluated the new riser location. The hydraulic calculations are still adequate.
|
Permit Ready to Issue | | | 8/19/2014 | | DONE |
|
|
|
|
Issue and Print Permit | | | 8/19/2014 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/19/2014 | | 8/19/2014 | | DONE |
Christina Prado
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/27/2014 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 6/27/2014 | | 6/27/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
Sprinkler Plan Check | 6/19/2014 | | 6/19/2014 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 6/19/2014 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 6/19/2014 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Plan assigned to (Tim) | 6/18/2014 | | 6/18/2014 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 6/11/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 11 2014 9:50PM
|