INSP-Final Inspection | 9/29/2014 | 9/30/2014 | 9/30/2014 | A | PASS |
Forrest France
|
|
|
Correction items completed. Fire sprinkler permit finaled.
|
INSP-Final Inspection | 9/25/2014 | 9/29/2014 | 9/29/2014 | P | PART |
Forrest France
|
|
|
UG fire supply line flush completed. Final overhead walkthrough also completed, outside bell tested okay. Items needed prior to final include; certify DCVA, provide inspectors test, missing escutcheon below stairway, noted several damaged escutcheons.
|
INSP-Sprinkler Rough-in/Hydro | 7/16/2014 | 7/17/2014 | 7/17/2014 | A | PASS |
Troy Cobbley
|
|
|
Tenting inspection passed on the second floor. All piping can be covered
|
INSP-Sprinkler Rough-in/Hydro | 7/15/2014 | 7/16/2014 | 7/16/2014 | A | FAIL |
Troy Cobbley
|
|
|
Second floor tenting is still not fixed
|
INSP-Sprinkler Rough-in/Hydro | 7/14/2014 | 7/15/2014 | 7/15/2014 | A | PART |
Troy Cobbley
|
|
|
Tenting on first floor is ok and piping can be covered. Second floor piping can not be covered due to tenting problems.
|
INSP-Sprinkler Rough-in | 7/9/2014 | 7/9/2014 | 7/9/2014 | P | PART |
Forrest France
|
|
|
UG fire supply line okayed for bury. Overhead rough-in inspection completed- *Need to meet min. spacing at pendent heads in three rooms affecting 8 heads total. Tenting is not installed at this time.
|
Permit Ready to Issue | | | 7/3/2014 | | DONE |
|
|
|
|
Issue and Print Permit | | | 7/3/2014 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/3/2014 | | 7/3/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (Tim) | 7/2/2014 | | 7/2/2014 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 7/2/2014 | | 7/2/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 7/2/2014 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/2/2014 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 6/18/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 18 2014 11:41AM
|