INSP-Final Inspection | 9/19/2014 | 9/19/2014 | 9/19/2014 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in | 9/18/2014 | 9/18/2014 | 9/18/2014 | P | PASS |
Troy Cobbley
|
|
|
Underground flush passed.
|
INSP-Sprinkler Rough-in/Hydro | 9/16/2014 | 9/17/2014 | 9/17/2014 | P | CANC |
Troy Cobbley
|
|
|
Underground hydro - Brandon Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 8/26/2014 | 8/27/2014 | 8/27/2014 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed and the tenting is now complete. Piping can be covered.
|
INSP-Sprinkler Rough-in | 8/26/2014 | 8/26/2014 | 8/26/2014 | P | FAIL |
Troy Cobbley
|
|
|
Tenting is still not complete.
|
INSP-Sprinkler Rough-in | 8/26/2014 | 8/26/2014 | 8/26/2014 | A | FAIL |
Troy Cobbley
|
|
|
Tenting is not complete. Piping can not be covered.
|
INSP-Sprinkler Rough-in | 8/25/2014 | 8/25/2014 | 8/25/2014 | P | PART |
Troy Cobbley
|
|
|
Sprinkler rough-in passed except missing on head in closet at lower level riser room. Piping can not be covered since tenting is incomplete.
|
INSP-Sprinkler Rough-in | 7/8/2014 | 7/8/2014 | 7/8/2014 | P | PASS |
Troy Cobbley
|
|
|
Underground ok to cover.
|
Permit Ready to Issue | | | 7/3/2014 | | DONE |
|
|
|
|
Issue and Print Permit | | | 7/3/2014 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/3/2014 | | 7/3/2014 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (Tim) | 7/2/2014 | | 7/2/2014 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 7/2/2014 | | 7/2/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 7/2/2014 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/2/2014 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 6/19/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 19 2014 1:32PM
|