INSP-Final Inspection | 12/18/2014 | 12/19/2014 | 12/19/2014 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 12/17/2014 | 12/18/2014 | 12/18/2014 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed
|
INSP-Sprinkler Rough-in/Hydro | 12/17/2014 | 12/17/2014 | 12/18/2014 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro passed
|
INSP-Sprinkler Rough-in | 10/27/2014 | 10/27/2014 | 10/27/2014 | P | PASS |
Troy Cobbley
|
|
|
oh rough to cover passed. tenting passed. piping can be covered
|
INSP-Supply line flush | 10/27/2014 | 10/27/2014 | 10/27/2014 | P | PASS |
Troy Cobbley
|
|
|
ug flush passed
|
INSP-Sprinkler Rough-in | 10/23/2014 | 10/23/2014 | 10/23/2014 | P | FAIL |
Troy Cobbley
|
|
|
Tenting still has not been repaired.. No piping can be covered.
|
INSP-Sprinkler Rough-in | 10/22/2014 | 10/22/2014 | 10/22/2014 | P | CANC |
Craig D. Hanson
|
|
|
Rough in good. Tenting needs to be re-inspected, not secured on pipe.
|
INSP-Sprinkler Rough-in | 7/17/2014 | 7/17/2014 | 7/17/2014 | P | PASS |
Troy Cobbley
|
|
|
Underground supply piping is ok to cover.
|
INSP-Sprinkler Rough-in | 7/9/2014 | 7/9/2014 | 7/9/2014 | P | CANC |
Troy Cobbley
|
|
|
underground - Brandon Phone #: ###-#### Inspection cancelled from web by: Barbara Stitt
|
INSP-Sprinkler Rough-in | 7/8/2014 | 7/9/2014 | 7/8/2014 | A | CANC |
Troy Cobbley
|
|
|
Wrong building called in.
|
Permit Ready to Issue | | | 7/3/2014 | | DONE |
|
|
|
|
Issue and Print Permit | | | 7/3/2014 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/3/2014 | | 7/3/2014 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (Tim) | 7/2/2014 | | 7/2/2014 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 7/2/2014 | | 7/2/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 7/2/2014 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/2/2014 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 6/19/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 19 2014 2:44PM
|