Case Summary | | | 2/2/2015 | | |
|
|
|
|
INSP-Final Inspection | 8/4/2014 | 8/4/2014 | 8/4/2014 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 7/31/2014 | 8/1/2014 | 8/1/2014 | A | CANC |
Troy Cobbley
|
|
|
Could not perform testing since Alarmco was not scheduled for the dialer inspection. I did however verify correct placement of the a/v's
|
Permit Ready to Issue | | | 7/2/2014 | | DONE |
|
|
|
|
Issue and Print Permit | | | 7/2/2014 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/2/2014 | | 7/2/2014 | | DONE |
Christina Prado
|
|
|
|
Application received | | | 7/1/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 1 2014 8:20AM
|
Plan assigned to (Lee) | 7/1/2014 | | 7/1/2014 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 7/1/2014 | | PASS |
|
|
|
|
Alarm Plan Check | 7/1/2014 | | 7/1/2014 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 7/1/2014 | | DONE |
|
|
|
Plans approved with review comments. Projectdox updated.
|