Permit Information
Permit NumberFIR14-00470
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 3003 W MAIN ST
Project Name30th & Main
Customer Number 
ePlanReviewYes
Description
The underground for this building was previously submitted (FIR14-00363) This is a submittal for the overhead system inside the building. This is a wet system with individual zones for each floor.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection11/24/201511/25/201511/25/2015APASS
DetailsJim Page
FIre sprinkler inspections completed on 12/30/2014 under FIR14-00363, all inspections complete for fire sprinklers.
INSP-Final Inspection12/30/201412/31/201412/31/2014APART
DetailsForrest France
Need to adjust PIV tamper and flow switch at the system riser 1st floor. Remainder of inspection passed.
INSP-Final Inspection12/29/201412/30/201412/30/2014APART
DetailsForrest France
Final pending sprinkler monitoring and associated fire alarm work. Remainder of C/N items finished.
INSP-Sprinkler Rough-in/Hydro12/29/201412/30/201412/30/2014APART
DetailsForrest France
Overhead hydrostatic test completed and passed for both new wet systems.
INSP-Final Inspection12/29/201412/29/201412/29/2014PPEND
DetailsForrest France
Jeff C. is your contact ###-####. Please call 1/2 hour prior to inspection. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Final Inspection12/23/201412/23/201412/26/2014PNR
DetailsForrest France
INSP-Final Inspection12/19/201412/22/201412/22/2014AFAIL
DetailsForrest France
C/N items include; missing coverage at the shell space first floor near exit door, overspaced upright coverage at the 2nd floor west side, missing seismic bracing at the top of the 4" feed main 2nd floor, ceiling tile and escutcheons yet to be installed in some areas of the 1st floor, need finish pack at the riser, permit activity notes do not indicate a hydrostatic test for the OH or UG has been completed.
INSP-Sprinkler Rough-in/Hydro10/30/201410/31/201410/31/2014PFAIL
DetailsCraig D. Hanson
heads need to installed in fireplace chase's. head needs installed in new room 1st floor S unit. As builts need to be submitted. Re-hydro after instilation of heads.
INSP-Sprinkler Rough-in10/28/201410/28/201410/28/2014PPART
DetailsForrest France
Okay to cover sheetrock lids as noted.
INSP-Sprinkler Rough-in10/1/201410/2/201410/2/2014PPART
DetailsForrest France
Overhead work okayed for cover at three restrooms, med gas room, and two soffits with sheetrock lids 1st floor as marked and dated on approved plans. Also discussed FDC location.
INSP-Sprinkler Rough-in9/9/20149/11/20149/9/2014ACANC
DetailsForrest France
Jeff is the contact.Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
Sprinkler Plan Check7/25/2014 7/25/2014 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  7/25/2014 DONE
DetailsTim Frost
Permit Ready to Issue  7/25/2014 DONE
DetailsTisha Gallop
Issue and Print Permit  7/25/2014 DONE
DetailsTisha Gallop
Inspection Record Card- Fire7/25/2014 7/25/2014 DONE
DetailsTisha Gallop
Plan assigned to (Tim)7/19/2014 7/19/2014 DONE
DetailsTim Frost
Sprinkler Plan Check7/19/2014 7/19/2014 FAIL
DetailsTim Frost
1st review completed  7/19/2014 FAIL
DetailsTim Frost
Miscellaneous action  7/19/2014 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Application received  7/7/2014 DONE
Application submitted via PDS Online on Jul 7 2014 11:30AM