INSP-Final Inspection | 12/22/2014 | 12/22/2014 | 12/22/2014 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 12/18/2014 | 12/19/2014 | 12/19/2014 | A | CANC |
Troy Cobbley
|
|
|
Rick Phone #: ###-####
|
INSP-Final Inspection | 12/17/2014 | 12/18/2014 | 12/19/2014 | A | CANC |
Troy Cobbley
|
|
|
Bernie, the general contractor, wanted life safety a priority so sprinkler inspection is being canceled.
|
INSP-Final Inspection | 12/17/2014 | 12/17/2014 | 12/17/2014 | P | PART |
Troy Cobbley
|
|
|
Forward flush passed. No other testing performed due to fire alarm communication problems.
|
INSP-Sprinkler Rough-in/Hydro | 12/16/2014 | 12/16/2014 | 12/16/2014 | P | PASS |
Troy Cobbley
|
|
|
North east room ceiling ok to install.
|
Sprinkler Plan Check | 12/9/2014 | | 12/9/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/9/2014 | | DONE |
Tim Frost
|
|
|
|
CHANGE STATUS TO (ISS) | | | 12/9/2014 | | DONE |
Candy A. Nichols
|
|
|
|
INSP-Sprinkler Rough-in | 11/25/2014 | 11/25/2014 | 11/25/2014 | P | PASS |
Troy Cobbley
|
|
|
Remaining ceilings are ok to install.
|
INSP-Sprinkler Rough-in/Hydro | 11/13/2014 | 11/13/2014 | 11/13/2014 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for additional rooms where piping can be covered.
|
INSP-Sprinkler Rough-in/Hydro | 11/7/2014 | 11/10/2014 | 11/10/2014 | A | PASS |
Troy Cobbley
|
|
|
24hr air test passed
|
INSP-Sprinkler Rough-in/Hydro | 11/6/2014 | 11/7/2014 | 11/7/2014 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed
|
INSP-Sprinkler Rough-in/Hydro | 11/5/2014 | 11/6/2014 | 11/6/2014 | A | DEFR |
Forrest France
|
|
|
Overbooked
|
INSP-Sprinkler Rough-in/Hydro | 10/23/2014 | 10/23/2014 | 10/23/2014 | P | PASS |
Troy Cobbley
|
|
|
Remaining hardlids ok to be installed and cover piping
|
INSP-Sprinkler Rough-in | 10/20/2014 | 10/20/2014 | 10/20/2014 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations where piping above the hardlids can be covered. I also performed a rough-in inspection for the remaining overhead piping. Additional cover inspections will be required.
|
INSP-Sprinkler Rough-in | 9/9/2014 | 9/10/2014 | 9/10/2014 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for "Entry" marked on the plans as OK to cover.
|
INSP-Sprinkler Rough-in | 9/4/2014 | 9/4/2014 | 9/4/2014 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for area clouded in red where rough-in is passed. Noted uprights slightly overspaced in small Storage Room.
|
INSP-Sprinkler Rough-in/Hydro | 8/14/2014 | 8/14/2014 | 8/14/2014 | P | PART |
Forrest France
|
|
|
UG fire supply line passed hydrostatic testing within allowable leakage per NFPA 13.
|
Permit Ready to Issue | | | 7/28/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Issue and Print Permit | | | 7/28/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Inspection Record Card- Fire | 7/28/2014 | | 7/28/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Sprinkler Plan Check | 7/25/2014 | | 7/25/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/25/2014 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 7/21/2014 | | 7/21/2014 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 7/21/2014 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 7/21/2014 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Plan assigned to (Tim) | 7/8/2014 | | 7/8/2014 | | DONE |
Scott Arellano
|
|
|
|
Telephone call | | | 7/8/2014 | | DONE |
Scott Arellano
|
|
|
Actually, emailed applicant (Chris Wilson) and reminded them to click the upload complete button on their end so the work flow can be initiated.
|
Application received | | | 7/7/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 7 2014 3:47PM
|