INSP-Final Inspection | 8/19/2015 | 8/20/2015 | 8/20/2015 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 8/18/2015 | 8/19/2015 | 8/19/2015 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro passed for the second floor
|
INSP-Sprinkler Rough-in/Hydro | 8/18/2015 | 8/18/2015 | 8/18/2015 | P | CANC |
Troy Cobbley
|
|
|
This is a rescheduled overhead hydro. Robert is the contact. Thanks. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 8/17/2015 | 8/18/2015 | 8/18/2015 | A | FAIL |
Troy Cobbley
|
|
|
Tried to perform overhead hydro test of the 2nd floor twice. It failed both times due to visible loss of pressure at the guage.
|
Plan assigned to (Tim) | 8/3/2015 | | 8/3/2015 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 8/3/2015 | | 8/3/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/3/2015 | | DONE |
Tim Frost
|
|
|
|
CHANGE STATUS TO (ISS) | | | 8/3/2015 | | DONE |
Christina Prado
|
|
|
|
(F) Reprint permit | | | 8/3/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/3/2015 | | 8/3/2015 | | DONE |
Brittany Hill
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 3/18/2015 | 3/18/2015 | 3/18/2015 | P | PART |
Troy Cobbley
|
|
|
Revised plans provided but one piece of pipe installed in the remote area does not match the city approved plans. Also verification needs to be provided for the exposed 2" cpvc pipe can remain exposed. Piping can be covered except for the piping in the remote area until sizing is settled through plan review or changed to match the approved drawings.
|
Sprinkler Plan Check | 3/16/2015 | | 3/16/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
Plan assigned to (Tim) | 3/16/2015 | | 3/16/2015 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/16/2015 | | DONE |
Tim Frost
|
|
|
|
CHANGE STATUS TO (ISS) | | | 3/16/2015 | | DONE |
Candy A. Nichols
|
|
|
|
INSP-Supply line flush | 2/26/2015 | 2/27/2015 | 2/27/2015 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed
|
INSP-Sprinkler Rough-in | 2/25/2015 | 2/25/2015 | 2/25/2015 | P | FAIL |
Troy Cobbley
|
|
|
Per review comments plan modifications are needed due to pipe route changes affecting hydraulic calculations. Piping can not be covered and a re-inspection will be required.
|
INSP-Supply line flush | 2/25/2015 | 2/25/2015 | 2/25/2015 | P | CANC |
Troy Cobbley
|
|
|
united water did not turn on water. could not perform flush
|
INSP-Sprinkler Rough-in | 9/19/2014 | 9/19/2014 | 9/19/2014 | P | PASS |
Troy Cobbley
|
|
|
Underground piping is ok to cover
|
INSP-Sprinkler Rough-in | 9/8/2014 | 9/11/2014 | 9/11/2014 | P | CANC |
Troy Cobbley
|
|
|
Cancel per John is the contact. Thanks Phone #: ###-#### Inspection requested via web by Stan Beus
|
Sprinkler Plan Check | 7/28/2014 | | 7/28/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 7/28/2014 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/28/2014 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 7/28/2014 | | DONE |
Barbara Stitt
|
|
|
|
Issue and Print Permit | | | 7/28/2014 | | DONE |
Barbara Stitt
|
|
|
|
Inspection Record Card- Fire | 7/28/2014 | | 7/28/2014 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (Tim) | 7/22/2014 | | 7/22/2014 | | DONE |
Scott Arellano
|
|
|
|
Sprinkler Plan Check | 7/22/2014 | | 7/22/2014 | | FAIL |
Tim Frost
|
|
|
Prescreen
|
Application received | | | 7/7/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 7 2014 4:43PM
|