Case Summary | | | 2/3/2015 | | |
|
|
|
|
Telephone call | | | 1/12/2015 | | DONE |
|
|
|
Rob Ahten called to request that duct detection for the crack unit be removed from the project and added just prior to completion due to construction dust clogging the filter.
|
INSP-Final Inspection | 1/8/2015 | 1/9/2015 | 1/9/2015 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled. Rob to submitt for work to remove the large vesda system that is currently shown on the city approved plans.
|
INSP-Final Inspection | 12/23/2014 | 12/23/2014 | 12/23/2014 | P | PART |
Troy Cobbley
|
|
|
A temporary for the fire alarm permit only is being given with scotts approval until the large Vesda system has been calibrated/inspected and the dust covers have been removed from all detectors.. Will need the NFPA record of completion forms as well.
|
INSP-Alarm Testing | 12/19/2014 | 12/22/2014 | 12/22/2014 | A | DONE |
Troy Cobbley
|
|
|
Continued testing on the fire alarm system which included the fire sprinkler system interconnections. I noted several overspaced strobes and discussed the Man Trap door operation.
|
INSP-Final Inspection | 12/18/2014 | 12/19/2014 | 12/19/2014 | A | CANC |
Troy Cobbley
|
|
|
Cancel per Robb Phone #: ###-####
|
INSP-Final Inspection | 12/16/2014 | 12/17/2014 | 12/17/2014 | P | CANC |
Troy Cobbley
|
|
|
Communication was down so no inspection was performed. Jonothan Phone #: ###-####
|
Telephone call | | | 12/17/2014 | | DONE |
|
|
|
Rob Ahten called to say that the Vesda detection system for the main plenum area requires 14 day of operation to fully acclimate to the environment. He wanted to know if, since this is a supplemental system, would a temporary occupancy be allowed during the acclimation period if all else passed. Troy Cobbley confirmed with Scott Arellano that a temp occupance would be allowed with a successful test of other systems and a final test of the Vesda system could be performed after the 14 days.
|
Miscellaneous action | | | 12/12/2014 | | DONE |
|
|
|
Troy Cobbley informed me that there were some changes on site regarding ceiling notification changing to wall maount an the addition of a paging interface that is connected to the fire alarm system. I emailed Rob Ahten to let him know that if it is just a few notification changes, this can be shown on as built drawings but if it is several that he needs to submit a plan mod for review. Also, if the page interface is via relays it can be on as built drawings but if it was a data interface, a plan mod will be required to review compatibility.
|
Telephone call | | | 12/12/2014 | | DONE |
|
|
|
Rob Ahten called to clarify that there will not be a paging interface. However, there will be water leak monitoring and card access interface. This work will be done after initial acceptance and will be performed a s a plan mod or T.I.
|
INSP-Alarm Testing | 12/9/2014 | 12/10/2014 | 12/11/2014 | P | DONE |
Troy Cobbley
|
|
|
Inspected/tested audio/visuals for the "industrial" portion of the building. Also did unit shut down. Need as-builts reflecting changes of a/v's from ceiling mount to wall mount and gererator power.
|
Permit Ready to Issue | | | 12/9/2014 | | DONE |
|
|
|
|
Issue and Print Permit | | | 12/9/2014 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 12/9/2014 | | 12/9/2014 | | DONE |
Brittany Hill
|
|
|
|
Alarm Plan Check | 12/8/2014 | | 12/8/2014 | | DONE |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 12/8/2014 | | DONE |
|
|
|
Plan modification approved with revised review comments. Projectdox updated.
|
Telephone call | | | 12/4/2014 | | DONE |
|
|
|
Rob Ahten called to say that the owner has elected to change the monitoring station interface from phone lines to an IP dialer. Rob requested that I reopen the case so he could upload changes. Case was failed on prescreen and reopened for this purpose.
|
Plan resubmittals received | | | 12/4/2014 | | DONE |
|
|
|
Plan modification received.
|
Telephone call | | | 12/3/2014 | | DONE |
|
|
|
Jonathan Ahten called to request the project be reopened to upload plan revisions. Project has been reopened.
|
Plan resubmittals received | | | 12/3/2014 | | DONE |
|
|
|
Plan mod revisions received.
|
Telephone call | | | 10/23/2014 | | DONE |
|
|
|
Rob Ahten called to discuss duct detection in the CRAC units. He is planning on pendant mounted photo sensors that are listed for the air volume in place of the sample tube detectors. H will be submitting a plan mod for this.
|
Permit Ready to Issue | | | 8/19/2014 | | DONE |
|
|
|
|
Issue and Print Permit | | | 8/19/2014 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/19/2014 | | 8/19/2014 | | DONE |
Christina Prado
|
|
|
|
Alarm Plan Check | 8/18/2014 | | 8/18/2014 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 8/18/2014 | | DONE |
|
|
|
Plans approved with review comments. Projectdox updated.
|
Plan resubmittals received | | | 8/13/2014 | | DONE |
|
|
|
|
Miscellaneous action | | | 8/12/2014 | | DONE |
|
|
|
Product manual and product data received from Rob Ahten. I emailed Rob to let him kow that there may be some sprinkler changes and that a meeting woud be tomorrow. 8-13-14.
|
1st review completed | | | 7/17/2014 | | FAIL |
|
|
|
See 1st review comments.
|
Miscellaneous action | | | 7/17/2014 | | DONE |
|
|
|
Rob Ahten emailed me to clarify the fact that the vesda system is voluntary and should not require calcs and design. I informed him that the code allows the non required equipment but requires that it be installed per code, as noted in the review comments.
|
Plan assigned to (Lee) | 7/10/2014 | | 7/10/2014 | | DONE |
Lee G Meredith
|
|
|
|
Miscellaneous action | | | 7/10/2014 | | DONE |
|
|
|
I emailed the applicant that the building department has not completed their project review and that my review will not be released until that is completed.
|
Application received | | | 7/9/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 9 2014 9:47AM
|