INSP-Final Inspection | 7/31/2014 | 7/31/2014 | 7/31/2014 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 7/30/2014 | 7/31/2014 | 7/31/2014 | A | PASS |
Troy Cobbley
|
|
|
Under ground hydro passed
|
INSP-Sprinkler Rough-in | 7/14/2014 | 7/14/2014 | 7/14/2014 | P | PASS |
Troy Cobbley
|
|
|
UG supply piping is ok to cover. Per discussion with fire sprinkler contractor (troy) and the excavator the dirt will need to come to the top of the footing or the required 4'-6" cover won't be available. Everybody stated that they understood.
|
Permit Ready to Issue | | | 7/14/2014 | | DONE |
Christina Prado
|
|
|
|
Issue and Print Permit | | | 7/14/2014 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 7/14/2014 | | 7/14/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (Scott) | 7/11/2014 | | 7/11/2014 | | DONE |
Scott Arellano
|
|
|
|
Sprinkler Plan Check | 7/11/2014 | | 7/11/2014 | | PASS |
Scott Arellano
|
|
|
No comments attached.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/11/2014 | | DONE |
|
|
|
|
Application received | | | 7/9/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 9 2014 3:18PM
|