INSP-Final Inspection | 11/20/2014 | 11/21/2014 | 11/21/2014 | P | PASS |
Forrest France
|
|
|
Final walkthrough passed. Scope of fire sprinkler work completed. Permit finaled.
|
INSP-Sprinkler Rough-in | 11/5/2014 | 11/6/2014 | 11/6/2014 | A | PART |
Forrest France
|
|
|
Noted corrections at previous inspection verified for completion. Overhead rough-in approved for ceiling cover.
|
INSP-Sprinkler Rough-in | 11/5/2014 | 11/5/2014 | 11/5/2014 | P | FAIL |
Forrest France
|
|
|
Noted several locations missing hanger restraint at pendent heads. Remove non-related trade work supported by fire protection piping.
|
Sprinkler Plan Check | 9/10/2014 | | 9/10/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/10/2014 | | DONE |
Tim Frost
|
|
|
|
CHANGE STATUS TO (ISS) | | | 9/10/2014 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 7/28/2014 | | DONE |
|
|
|
|
Issue and Print Permit | | | 7/28/2014 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/28/2014 | | 7/28/2014 | | DONE |
Christina Prado
|
|
|
|
Sprinkler Plan Check | 7/26/2014 | | 7/26/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/26/2014 | | DONE |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 7/22/2014 | | 7/22/2014 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 7/22/2014 | | 7/22/2014 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 7/22/2014 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 7/22/2014 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 7/11/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 11 2014 1:40PM
|