Case Summary | | | 6/3/2016 | | DONE |
|
|
|
|
INSP-Final Inspection | 1/19/2016 | 1/20/2016 | 1/20/2016 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
Telephone call | | | 1/6/2016 | | DONE |
|
|
|
Scott Arrelano received a call from the property manager indicating roof top units 14 and 15 will be decommissioned from use. Both units are to have electrical and gas connections removed and locked out from further use. They are to be abandonded in place due to prohibitive cost of removing them.
|
Miscellaneous action | | | 1/6/2016 | | DONE |
|
|
|
Marv Meyer of Russell Corp. sent a pdf file that shows all rooftop HVAC equipment locations including units 14 and 15 that are being decommissioned. The drawing has been uploaded into documents.
|
INSP-Final Inspection | 2/3/2015 | 2/4/2015 | 2/4/2015 | A | FAIL |
Troy Cobbley
|
|
|
Waiting for hvac units to be repaired or removed so the remaining duct detectors can be tested for shutdown.
|
INSP-Final Inspection | 2/2/2015 | 2/3/2015 | 2/3/2015 | A | FAIL |
Troy Cobbley
|
|
|
The FACP, fire sprinkler devices, batteries, smoke detector, pull station and several duct smoke detectors tested ok today. Will need to finish testing of the remaining duct smoke detectors prior to a final. Will also need document box, map and knox box.
|
INSP-Final Inspection | 1/30/2015 | 2/2/2015 | 2/2/2015 | A | PEND |
Forrest France
|
|
|
Discussed plan modification and date reviewed, project schedule and RTU installations.
|
Plan resubmittals received | | | 2/2/2015 | | DONE |
|
|
|
Two copies of Application/booklet, FA00 and FA20
|
Alarm Plan Check | 2/2/2015 | | 2/2/2015 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 2/2/2015 | | DONE |
|
|
|
Plan mod / as built approved with review comments. Taken to front desk for processing.
|
Permit Ready to Issue | | | 2/2/2015 | | DONE |
Candy A. Nichols
|
|
|
DO NOT RE ISSUE
|
Telephone call | | | 2/2/2015 | | DONE |
Candy A. Nichols
|
|
|
called Greg to let know plan mod is ready to be picked up. Told him the amount due-do not re-issue
|
CHANGE STATUS TO (ISS) | | | 2/2/2015 | | DONE |
|
|
|
|
INSP-Final Inspection | 8/8/2014 | 8/8/2014 | 8/8/2014 | P | FAIL |
Troy Cobbley
|
|
|
Provide city approved data sheets and as-built drawings/complete submittals as dsicussed. Functional testing of system passed.
|
CHANGE STATUS TO (ISS) | | | 8/8/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (Lee) | 7/21/2014 | | 7/28/2014 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 7/28/2014 | | PASS |
|
|
|
|
Alarm Plan Check | 7/28/2014 | | 7/28/2014 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 7/28/2014 | | DONE |
|
|
|
Review passed. As built floor plans with calculations to be provided at acceptance test. Documents taken to front desk for processing.
|
Telephone call | | | 7/28/2014 | | DONE |
Christina Prado
|
|
|
Called Greg to advise permit is ready for pick up and gave fees due
|
Permit Ready to Issue | | | 7/28/2014 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 7/28/2014 | | 7/28/2014 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 7/22/2014 | | DONE |
|
|
|
Mary Froemke call to say that the perminant power for this site (BLD14-01680) was being removed and temporary power was being supplied until the demo work was finished and the existing building was seperated into 2 buildings. Because of this, the existing fire alarm system will need to be repaced and 2 systems installed. To keep sprinkler monitoring intact, new panels will be installed. A plan modification will be submitted with floor plans showing vanilla finish sprinkler montioring. I informed her that this was acceptable to keep the systems properly monitored but systems will need to have all required detection and off site monitoring installed ASAP to insure constant monitoring. (Also see FIR14-00518)
|
Application received | | | 7/21/2014 | | |
|
|
|
|