INSP-Final Inspection | 10/21/2014 | 10/22/2014 | 10/22/2014 | A | PASS |
Forrest France
|
|
|
UG fire supply line flush completed satisfactory. UG permit work finished, okay for final.
|
INSP-Sprinkler Rough-in | 10/17/2014 | 10/20/2014 | 10/20/2014 | A | CANC |
Troy Cobbley
|
|
|
Cancel per Troy-underground flush Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 7/29/2014 | 7/29/2014 | 7/29/2014 | P | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed
|
INSP-Sprinkler Rough-in/Hydro | 7/24/2014 | 7/25/2014 | 7/25/2014 | A | PART |
Scott Arellano
|
|
|
OK to cover supply pipe.
|
Plan assigned to (Tim) | 7/24/2014 | | 7/24/2014 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 7/24/2014 | | 7/24/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 7/24/2014 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/24/2014 | | DONE |
Tim Frost
|
|
|
|
Issue and Print Permit | | | 7/24/2014 | | DONE |
Tisha Gallop
|
|
|
|
Inspection Record Card- Fire | 7/24/2014 | | 7/24/2014 | | DONE |
Tisha Gallop
|
|
|
|
Application received | | | 7/21/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 21 2014 4:01PM
|