Permit Information
Permit NumberFIR14-00533
StatusFinaled
Name ABSOLUTE FIRE PROTECTION
Site Address 8743 W HACKAMORE DR
Project NameLandmark Apartments Bldg #1
Customer Number 
ePlanReviewYes
Description
The fire sprinkler scope of work consists of protecting, (4) two level apartments (townhouses). CPVC piping and extended coverage sprinklers are being utilized. The underground is 2” poly pipe. There will be a 1½” FDC.

To construct a new 3,668 sq. ft., two story, Four unit, apartment building. Units 'A' have one bedroom, one den, and two bathrooms. Units 'B' have two bedrooms, and two bathrooms. All 4 dwelling units have their own independent exit. All construction per the approved plans, attached plan review report, and all other reviewing agencies approvals. One hour fire-partition separations are required between dwelling units.

Contractor’s Note:
The building permit has not been issued at this time. The building department may determine that changes are required to the building plans in order to meet code. The changes may affect the sprinkler system. The sprinkler contractor will be obligated to make all necessary changes that may be required. Therefore, if the sprinkler contractor chooses to proceed without an issued building permit, they will do so on their own cognizance. This note does not constitute an early start agreement.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection11/19/201411/21/201411/21/2014PPASS
DetailsTroy Cobbley
permit finaled
INSP-Sprinkler Rough-in/Hydro11/19/201411/19/201411/19/2014PPASS
DetailsTroy Cobbley
Overhead hydro passed
INSP-Sprinkler Rough-in/Hydro11/18/201411/18/201411/18/2014PPASS
DetailsTroy Cobbley
Underground flush passed
INSP-Sprinkler Rough-in10/14/201410/14/201410/14/2014PPASS
DetailsTroy Cobbley
Tenting passed. Piping can be covered.
INSP-Sprinkler Rough-in10/13/201410/14/201410/14/2014AFAIL
DetailsTroy Cobbley
tenting inspection failed
INSP-Sprinkler Rough-in10/7/201410/8/201410/8/2014PPASS
DetailsTroy Cobbley
Rough-in passed. Piping can not be covered until a tenting inspection has been performed.
INSP-Sprinkler Rough-in8/26/20148/26/20148/26/2014PPASS
DetailsTroy Cobbley
Underground ok for cover
Permit Ready to Issue  8/4/2014 DONE
DetailsTisha Gallop
Issue and Print Permit  8/4/2014 DONE
DetailsTisha Gallop
Inspection Record Card- Fire8/4/2014 8/4/2014 DONE
DetailsTisha Gallop
Plan assigned to (Tim)8/1/2014 8/1/2014 DONE
DetailsTim Frost
Sprinkler Plan Check8/1/2014 8/1/2014 PASS
DetailsTim Frost
Please, see attached comments.
1st review completed  8/1/2014 PASS
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  8/1/2014 DONE
DetailsTim Frost
Application received  7/25/2014 DONE
Application submitted via PDS Online on Jul 25 2014 6:29AM